Factory Establishment and Licensing in Bangladesh
We guide local and foreign manufacturers through factory establishment in Bangladesh: DIFE layout plan approval and factory licence, Invest Bangladesh or BEPZA registration, environmental clearance, fire, building and boiler approvals, trade licences, import registration and the compliance needed to start production and stay licensed.
- Project scoping
- Registration and applications
- Inspections and licences
- Compliance and renewal
Factory establishment in Bangladesh: approvals, sequencing and compliance
Bangladesh remains one of the world's most important manufacturing locations, from garments, textiles and leather to pharmaceuticals, food processing, plastics, light engineering and electronics assembly. Every new plant, extension or relocation, however, must pass through a series of approvals before production can lawfully begin. Factory establishment in Bangladesh is therefore as much a regulatory project as a construction one, and delays in a single approval can hold up machinery imports, bank financing and buyer audits. We advise manufacturers on this process as part of our regulatory practice in Bangladesh. Good factory establishment planning can save months.
At the centre of the process is the Department of Inspection for Factories and Establishments (DIFE). Under the Labour Act 2006, as amended, and the Bangladesh Labour Rules 2015, a factory's layout plan must be approved before construction or conversion, and the factory must obtain a licence before operating and renew it on time. Applications now run largely through DIFE's online portal, and the Act provides a time-limited appeal against refusal. Because the Labour Act and Rules have been amended more than once in recent years, current requirements should always be checked against the latest texts and portal guidance.
Other authorities sit alongside DIFE. Projects need registration with Invest Bangladesh, which since 23 August 2026 has taken over the investment functions previously carried out by BIDA and BEZA, or with BEPZA for factories inside export processing zones. Environmental clearance from the Department of Environment is required under the Environment Conservation Act 1995 and the Environment Conservation Rules 2023, with the industry category determining the process. Building approval from RAJUK or the local authority, a fire licence from the Fire Service and Civil Defence, boiler registration and certificates of use, a trade licence and utility connections may also be needed.
Sequencing is where projects succeed or fail. Some approvals require others to be in place first: environmental clearance may require site and layout details, DIFE may expect building and fire approvals, and banks will not open machinery import LCs without the right registrations. Buying or leasing an existing factory adds further risk, because the licences, clearances and compliance history of the previous operator do not always transfer cleanly. Export-oriented manufacturers also face buyers' social and safety audits, structural and fire safety standards and, for garments, the expectations of industry safety programmes, which often go beyond the legal minimum.
We help clients plan and manage each factory establishment project from site selection to first production. That includes reviewing land and lease documents, mapping every approval with realistic timelines, preparing applications and supporting documents, dealing with authority queries and inspections, and setting up the compliance systems needed to renew licences and pass audits each year. Where a project is foreign owned, we also handle company formation, foreign exchange and Invest Bangladesh steps. For a project planning discussion, contact our Dhaka office, or read about our wider corporate practice. We work in English and Bangla.
Core workstreams
Four clear stages
- 01Project scoping
- 02Registration and applications
- 03Inspections and licences
- 04Compliance and renewal
Talk to a partner
Consultations in Dhaka or by video. Scope, team and fees are agreed in writing first.
Book →How we support new factories, expansions and relocations
Approval mapping and project planning
- Project scoping
- Registration and applications
- Inspections and licences
- Compliance and renewal
DIFE layout approval and factory licence
- Project scoping
- Registration and applications
- Inspections and licences
- Compliance and renewal
Investment and zone registration
- Project scoping
- Registration and applications
- Inspections and licences
- Compliance and renewal
Environmental, fire and building approvals
- Project scoping
- Registration and applications
- Inspections and licences
- Compliance and renewal
Acquisitions and existing factories
- Project scoping
- Registration and applications
- Inspections and licences
- Compliance and renewal
Ongoing compliance and inspections
- Project scoping
- Registration and applications
- Inspections and licences
- Compliance and renewal
Approval mapping and project planning
We review the planned product, process, capacity, workforce size, site and ownership, then prepare an approvals map that lists every licence, clearance and registration needed for factory establishment, the authority responsible, the documents required, dependencies between approvals and realistic timelines. The map becomes the working plan for the project team, contractors, lenders and the board. Factory establishment risks are flagged early. Updates follow as circumstances change. Each approval is allocated to a named person with a target date, so responsibility is clear.
DIFE layout approval and factory licence
We prepare and review applications for layout plan approval and factory licences through DIFE's portal, check drawings and safety provisions against the Labour Rules, coordinate with architects and engineers, and respond to inspector queries. We also manage licence renewals, amendments for changes in capacity, workforce, ownership or address, and appeals where an application is refused or delayed without reason. Each factory establishment file is kept complete. Renewal dates are diarised well ahead so that licences do not lapse during production.
Investment and zone registration
We handle project registration with Invest Bangladesh for local, foreign and joint venture projects, and BEPZA registration and agreements for factories in export processing zones. We align the company's constitutional documents, project profile and factory address across every registration, so that later approvals, import entitlements, work permits for foreign staff and bank facilities are not delayed by inconsistent records. We also handle amendments when the project changes.
Environmental, fire and building approvals
We coordinate applications for site and environmental clearance with the Department of Environment, including effluent treatment and impact assessment requirements for higher-risk categories, building plan approval, fire licences and fire safety plans, and boiler registration and certificates of use. We help engineers and consultants present documents correctly and track conditions attached to each approval through to renewal. Approvals are tracked against factory establishment milestones. Consultants are briefed on legal requirements.
Acquisitions and existing factories
When clients buy, lease or take over an operating factory, we review the existing licences, clearances, inspection reports, labour disputes and compliance history, identify which approvals can be transferred or amended and which must be obtained afresh, and draft protections in the sale or lease documents. This reduces the risk of inheriting unpaid dues, safety defects or enforcement action. Factory establishment timelines are protected through warranties and conditions.
Ongoing compliance and inspections
After start-up we help manufacturers maintain compliance: licence renewals, registers and notices required under the Labour Act, safety committees, welfare facilities, workers' participation fund obligations where applicable, and environmental and fire safety conditions. We prepare clients for DIFE and other inspections, respond to notices and represent them in proceedings arising from alleged breaches. Compliance records are kept ready for audits. We also train site managers. Replies to authority notices are drafted with supporting evidence, since vague answers often prolong enforcement.
Partner-led, on every matter.
Trade, Competition & Regulation matters at TRW are led by partners, supported by associates, with one responsible lawyer from first advice to final outcome.
Meet the firm →01Which factory establishment approvals are needed before we start construction in Bangladesh?
Before building works begin, a manufacturer usually needs secure title or a registered lease of the site, building plan approval from RAJUK or the relevant local authority, DIFE approval of the factory layout plan, and site or environmental clearance from the Department of Environment depending on the industry category. Fire safety design should also be agreed with the Fire Service and Civil Defence. Projects normally register with Invest Bangladesh or BEPZA at an early stage. We prepare a factory establishment approvals map at the start, so that construction does not run ahead of approvals that later prove difficult to obtain.
02How long does it take to obtain a DIFE factory licence?
Timing depends on the completeness of the application, the type of factory, the inspection schedule and whether other approvals, such as building and fire clearances, are in place. Where documents are in order, DIFE's online process can move reasonably quickly, but missing drawings, inconsistent records or safety queries often cause delays of weeks or months. Apply well before the planned start of production. We review applications before filing to reduce the risk of queries, and follow up with the department during processing so that issues are dealt with promptly. Good factory establishment planning builds this into the timetable.
03Do factories in export processing zones need DIFE approval?
Factories within EPZs are regulated by BEPZA, which has its own framework for labour, safety and licensing matters inside the zones, including its own labour legislation for zone enterprises. In practice, enterprises in EPZs deal primarily with BEPZA rather than DIFE for approvals and inspections. Economic zones are subject to different arrangements, now administered by Invest Bangladesh following the 2026 merger. The precise position should be checked for each zone and activity. We advise zone investors on factory establishment requirements specific to their location and on how zone rules interact with national laws. Zone documentation should be confirmed early.
04What happens if we start production before completing factory establishment approvals?
Operating a factory without the required licence or approved layout plan can lead to penalties under the Labour Act, enforcement notices, and in serious cases closure orders, particularly if safety risks are identified. It can also cause practical problems: banks may refuse facilities, insurers may question cover, customs entitlements may be affected and international buyers may suspend orders after an audit. If production has already begun, the safest course is to regularise the position quickly. We advise on the steps to bring the factory into compliance and on dealing with any notices received. Gather existing approvals and receipts first.
05Can a foreign company own and operate a factory in Bangladesh?
Yes. Most manufacturing sectors are open to full foreign ownership, subject to limited restrictions in certain regulated or reserved activities. A foreign investor typically incorporates a Bangladeshi company, registers the project with Invest Bangladesh or BEPZA, brings in capital through banking channels with the required encashment documents, and then obtains the same factory licences as a local manufacturer. Work permits are needed for foreign staff. We handle the corporate, foreign exchange and investment steps alongside the factory establishment approvals, so that the two tracks move in parallel rather than one after the other. Keep the capital inflow documents.
06Do we need new factory establishment approvals to expand or relocate an existing plant?
Usually yes. An expansion that changes floor area, layout, machinery, capacity or workforce numbers generally requires an amended DIFE layout approval and licence, and may require updated environmental clearance, fire safety approval and building permissions. A relocation to a new site is treated much like new factory establishment, although existing registrations can sometimes be amended rather than replaced. Investment registrations and import entitlements may also need updating. We review the planned change, identify what must be amended and in what order, and help avoid gaps that could interrupt production. Amendments should be planned early. Check loan terms for notice requirements.
07How does environmental clearance work for a new manufacturing plant?
Under the Environment Conservation Rules 2023, industrial units are classified into categories according to their potential environmental impact. Lower-risk categories follow a simpler process, while higher-risk industries, such as dyeing, tanning, chemicals and many heavy industries, require site clearance, an environmental impact assessment, an approved effluent treatment plant and, before operation, environmental clearance. Clearances must be renewed and their conditions monitored. Weak environmental compliance is a common reason for buyer concerns and enforcement action. We work with environmental consultants to prepare applications and manage conditions throughout the project. Site clearance generally precedes construction. Consultants should be engaged early.
08What compliance obligations continue after the factory is licensed?
A licensed factory must renew its licence and other approvals on time, keep the registers and notices required by the Labour Act and Rules, maintain safety and welfare facilities, form safety and other committees where the workforce size requires them, and comply with conditions attached to environmental, fire and boiler approvals. Changes in capacity, ownership or address must be notified or approved. Inspections can happen at any time. We help clients set up compliance calendars and internal audits, and represent them if notices or prosecutions follow an inspection. Factory establishment does not end with the first licence.
From first call to resolution.
- 01
Project scoping
We review the product, process, site, ownership and timetable, identify the factory establishment approvals required and their sequence, and highlight risks such as land title issues, zoning restrictions or environmental category concerns. We explain costs and realistic timelines at the outset.
- 02
Registration and applications
We complete company and investment registration where needed, then prepare and file applications for layout, building, environmental, fire and boiler approvals in the right order, working closely with the client's engineers. Each filing is logged with its reference number and expected decision date. Authority queries are answered quickly, with engineers' input where technical points arise.
- 03
Inspections and licences
We follow applications through to decision, respond to authority queries, support inspections and site visits, and obtain the factory licence and remaining permits needed before commercial production begins. We keep management informed of every decision and condition. Licence conditions are recorded in a compliance calendar so later renewals and inspections are not missed.
- 04
Compliance and renewal
We set up a compliance calendar for renewals, registers and committees, support audits and inspections, and manage amendments when the factory expands, changes ownership or relocates. Renewal reminders are managed for each approval. Audits are prepared in advance.
“Demonstrates an extraordinary command over both domestic litigation and international arbitration.”
The Legal 500 Asia Pacific, Bangladesh: Dispute resolution, client feedback
Related reading.

Factory License in Bangladesh: DIFE Layout Plan Approval, Licence and Renewal in 2026

Factory Setup in Bangladesh: a 2026 Compliance Planning Guide

Fire License in Bangladesh: Fire Service Licence Process, Building Clearance and Penalties in 2026

Environmental Compliance in Bangladesh 2026: ECC Renewal, ETPs, Inspections and Penalties
All insights →
What is DIFE and what is its role in factory establishment?
Is a trade licence enough to run a factory?
Do small workshops need a factory licence?
Can factory approvals be transferred to a buyer?
What is Invest Bangladesh's role in factory establishment?
Are fire licences required for all factories?
How can we check a factory's licence status before buying or leasing it?
How can TRW help with our factory establishment project?
Plan your factory approvals from day one
Speak with the partners about factory establishment in Bangladesh or across borders.
Book a consultation →