Construction Claims & Project Disputes in Bangladesh
Advice and representation on construction claims and project disputes in Bangladesh for contractors, employers, developers, consultants and lenders: delay and disruption, unpaid certificates, variations, termination, bank guarantee calls, dispute boards, arbitration and court proceedings, from the very first notice through to final enforcement.
- Rapid issue review
- Build the claim
- Negotiate and escalate
- Resolve and enforce
How we handle construction claims and project disputes
Construction projects in Bangladesh are large, complex and often run under intense time and budget pressure. Late site access, design changes, ground conditions, delayed approvals, currency movements, unpaid certificates and disagreements over quality can quickly turn into construction claims worth a significant share of the contract price. We act for contractors, subcontractors, employers, developers, consultants and lenders on public and private projects, from power plants, roads and bridges to factories, economic zone facilities, commercial towers and housing. Our aim is to protect the client's position early, preserve commercial options and, where a dispute cannot be avoided, pursue it efficiently.
Most claims are won or lost on the contract and the record. The contract decides what notices must be given, when, to whom and in what form, and many FIDIC-based contracts used in Bangladesh impose strict time limits that can bar an otherwise valid claim. The project record shows what actually happened: programmes, site diaries, correspondence, minutes, instructions, payment certificates and photographs. We help clients organise this material while the project is still running, so that construction claims are supported by contemporaneous evidence rather than reconstructed later, when memories have faded and key people have moved on.
We look at the commercial picture behind construction claims. A contractor may want to recover cost and time while keeping a good relationship with a repeat employer. An employer may need to keep a project moving while resisting inflated claims and protecting public funds. A lender may be concerned about completion risk and security. We advise on negotiation strategy, engineer's determinations, dispute board referrals, mediation and settlement, and we prepare for arbitration or litigation in parallel, so the client is never forced to accept a poor deal because the formal route has not been prepared.
When construction claims reach formal proceedings, the forum matters. Many construction contracts provide for arbitration in Dhaka or abroad, governed in Bangladesh by the Arbitration Act 2001. Court disputes may now fall within the Commercial Courts Act 2026, and the Legal Aid Services (Amendment) Act 2026 is introducing mandatory pre-case mediation for certain disputes on a district-by-district basis. Public contracts may have their own review mechanisms. Our work draws on the firm's dispute resolution practice and our projects and real estate team, combining advocacy experience with knowledge of how projects are built. Forum choice shapes cost and speed.
Cross-border projects add further layers. Foreign contractors and suppliers may face claims under contracts governed by English or other foreign law, with arbitration seated in Singapore, London or another centre, while assets, guarantees and project sites are in Bangladesh. We work with counsel in the UK, US, UAE, China, India and Singapore and handle the Bangladesh-law aspects, including interim relief, bank guarantee injunctions, enforcement of awards and local regulatory issues. The Legal 500 Asia Pacific ranks Tahmidur Remura Wahid (TRW) Law Firm for dispute resolution in Bangladesh, and our partners combine arbitration, litigation and transactional experience.
Core workstreams
Four clear stages
- 01Rapid issue review
- 02Build the claim
- 03Negotiate and escalate
- 04Resolve and enforce
Talk to a partner
Consultations in Dhaka or by video. Scope, team and fees are agreed in writing first.
Book →Construction claims and disputes we handle
Delay and disruption claims
- Rapid issue review
- Build the claim
- Negotiate and escalate
- Resolve and enforce
Variations and payment
- Rapid issue review
- Build the claim
- Negotiate and escalate
- Resolve and enforce
Defects, quality and completion
- Rapid issue review
- Build the claim
- Negotiate and escalate
- Resolve and enforce
Termination and suspension
- Rapid issue review
- Build the claim
- Negotiate and escalate
- Resolve and enforce
Bank guarantee calls
- Rapid issue review
- Build the claim
- Negotiate and escalate
- Resolve and enforce
Arbitration and litigation
- Rapid issue review
- Build the claim
- Negotiate and escalate
- Resolve and enforce
Delay and disruption claims
We prepare and defend claims for extension of time, prolongation costs, acceleration and disruption, working with planning and quantum experts. We review the contract's entitlement provisions, notice requirements and programme obligations, analyse the causes of delay and concurrency, and present construction claims in a structured way that an engineer, dispute board or tribunal can follow and test against the record without difficulty. Concurrent delay arguments are tested early.
Variations and payment
Unpaid certificates and disputed variations are the most common sources of conflict on Bangladesh projects. We advise on valuation of variations, interim payment applications, retention, price adjustment and foreign exchange provisions, set-off and withholding, and remedies for late payment, including suspension, interest and termination. We also help subcontractors pursue payment through the supply chain and assess pay-when-paid and back-to-back terms. Cash flow pressure is often the real issue, so we focus on practical routes to payment.
Defects, quality and completion
We act on disputes about defective work, testing and commissioning failures, taking-over certificates, performance guarantees and defects liability. We help employers assess remedies, including liquidated damages, deduction of rectification costs and calls on security, and help contractors respond to defect allegations, challenge inflated counterclaims and secure release of retention and guarantees at the end of the defects period. Expert evidence on defects is coordinated from the outset. Retention release is tracked closely.
Termination and suspension
Termination is one of the highest-risk steps on any project. We advise employers and contractors on the grounds and procedure for termination or suspension under the contract and general law, the consequences for payment, plant, materials and subcontracts, and steps to protect the site, records and security. Getting the sequence right can decide whether termination is upheld or becomes a wrongful repudiation. We also advise on construction claims that follow termination.
Bank guarantee calls
Performance, advance payment and retention guarantees are frequently called when a dispute arises. We advise beneficiaries on making compliant demands and advise contractors on the narrow grounds on which Bangladesh courts may restrain payment, such as established fraud. We prepare urgent applications where justified and coordinate with arbitration proceedings so that the guarantee dispute and the underlying claim are handled consistently. Guarantee wording is reviewed before any demand is made.
Arbitration and litigation
We represent clients in domestic and international arbitration, dispute board proceedings and court litigation arising from construction claims, including challenges to awards and enforcement. We manage documents, witnesses and experts, prepare pleadings and submissions, and advocate at hearings. For cross-border disputes we work alongside foreign counsel and handle interim relief and enforcement steps in Bangladesh. Strategy is set with the client's commercial goals in mind. Costs are kept under review.
Partner-led, on every matter.
Projects & Real Estate matters at TRW are led by partners, supported by associates, with one responsible lawyer from first advice to final outcome.
Meet the firm →01What should a contractor do first when a delay event occurs?
First, check the contract's notice provisions and give notice in the required form and time, even if the full effect of the event is not yet known. Many FIDIC-based contracts require notice within 28 days of the contractor becoming aware of the event, and missing that deadline can bar the claim. Second, start recording the impact: update the programme, keep site diaries, photographs and correspondence, and track additional costs separately. Early, accurate notices are the foundation of successful construction claims, and we can review the draft notice before it is sent to the engineer or employer.
02How are construction claims usually resolved in Bangladesh?
Most construction claims are resolved through negotiation, often after an engineer's determination or a dispute board decision. Where agreement is not possible, the contract usually provides for arbitration, which may be seated in Dhaka under the Arbitration Act 2001 or abroad under institutional rules. Some contracts and many smaller disputes go to court, where the Commercial Courts Act 2026 may apply, and mandatory pre-case mediation is being introduced for certain disputes. Public contracts may include administrative review steps. We advise on the route that fits the contract, the amount at stake and the client's commercial goals.
03Can an employer in Bangladesh deduct liquidated damages for contractor delay?
An employer can generally claim liquidated damages if the contract provides for them, the contractor has failed to complete by the relevant date and no extension of time is due. Bangladesh courts apply the Contract Act 1872, under which a stipulated sum is generally treated as a maximum and the court awards reasonable compensation not exceeding it, so the amount is not automatically recoverable in full. Employer-caused delay, a failure to grant justified extensions or defective contract machinery may also undermine the claim. We advise employers on deductions and contractors on challenging them as part of wider construction claims.
04Can a Bangladesh court stop a bank from paying a performance guarantee?
Bangladesh courts generally treat unconditional bank guarantees as independent of the underlying contract, so the bank must pay a compliant demand even if the construction dispute is unresolved. Courts may restrain payment only on narrow grounds, such as established fraud known to the bank or circumstances that would cause irretrievable injustice, and the threshold is high. A demand that does not comply with the guarantee's terms may also be refused. Because time is short once a demand is made, contractors should review guarantee wording before disputes arise and seek advice immediately if a call appears likely.
05How long do contractors have to bring construction claims?
Two sets of time limits matter. The contract may impose short notice periods and deadlines for referring disputes to a dispute board or arbitration, which can be strictly enforced. The Limitation Act 1908 then sets general statutory periods for court suits, and those periods are also relevant to arbitration. Calculating limitation can be complicated where a project runs for several years, payments are made in instalments or acknowledgements are given. We review both contractual and statutory deadlines at the start of any matter, because a late claim can fail regardless of its merits. Diarising deadlines in construction claims is essential.
06Are dispute boards used on Bangladesh projects?
Yes, particularly on large infrastructure projects funded by development partners and contracts based on FIDIC conditions, which provide for dispute adjudication or avoidance boards. A board can help resolve issues during construction and reduce the risk of a backlog of disputes at completion. Its decisions are usually binding unless and until revised by settlement or arbitration, and a party that disagrees must normally give a notice of dissatisfaction within a short period. We prepare referrals, respond to referrals and advise on whether and how to challenge a decision in later proceedings involving construction claims. Board decisions deserve prompt review.
07Can a foreign arbitral award on a construction dispute be enforced in Bangladesh?
Yes. Bangladesh is a party to the New York Convention, and the Arbitration Act 2001 provides for recognition and enforcement of foreign arbitral awards made in other Convention states, subject to limited grounds for refusal such as incapacity, invalid agreement, lack of proper notice or conflict with public policy. Enforcement proceedings are brought before the competent court, and the award debtor may resist. Practical issues such as locating assets, currency conversion and timing should be considered early. We advise award creditors and debtors on enforcement strategy and act in the enforcement proceedings. Recovery planning should start early.
08Should we settle construction claims or go to arbitration?
It depends on the strength of the claim, the evidence, the cost and time of proceedings, the counterparty's ability to pay and the value of the commercial relationship. Arbitration can be expensive and may take a considerable time, while settlement offers certainty and preserves cash flow. A strong, well-documented claim usually produces a better settlement, so preparing for arbitration often improves negotiation. Mediation can help where talks have stalled. We give a candid assessment of prospects, costs and risks and help clients decide when to settle and when to press on. Timing also matters a great deal.
From first call to resolution.
- 01
Rapid issue review
We review the contract, notices, correspondence and the event that triggered the claim, identify urgent deadlines and advise on immediate steps to protect entitlement, security and evidence. This first review is fast and focused, so the client can make immediate decisions with confidence.
- 02
Build the claim
We gather and organise the project record, work with planning and quantum experts and prepare or respond to construction claims in a clear, evidence-based format that supports negotiation and formal referral. Weak points are identified honestly, so the claim can be strengthened before it is tested.
- 03
Negotiate and escalate
We pursue negotiation, engineer's determinations, dispute board referrals and mediation, while preparing arbitration or court proceedings in parallel so the client keeps leverage at every stage. Construction claims are often settled most effectively at this stage, with leverage intact.
- 04
Resolve and enforce
We represent clients through hearings, settlements and awards, then advise on challenges, enforcement and recovery against assets in Bangladesh or abroad, coordinating with foreign counsel where needed. Recovery is planned from the outset of the dispute. Enforcement is pursued with persistence.
“Demonstrates an extraordinary command over both domestic litigation and international arbitration.”
The Legal 500 Asia Pacific, Bangladesh: Dispute resolution, client feedback
Related reading.

Construction Arbitration in Bangladesh 2026: Claims, Dispute Boards, Public Contracts and Plant Disputes
Unpaid on a Bangladesh Infrastructure Project? Protecting Claims Before Deadlines Expire
Can a Performance Guarantee Be Stopped in Bangladesh? What Contractors Must Know

Commercial Courts Act Bangladesh 2026: Jurisdiction, Procedure, Interest and Appeals
All insights →
What are construction claims?
Do you act for employers as well as contractors?
What records help most in construction claims?
Can disputes be resolved while work continues?
Does mandatory mediation apply to construction disputes?
What experts are needed in construction claims?
Can subcontractors claim directly against the employer?
How do we instruct TRW & Co on construction claims?
Protect your project position before deadlines pass
Speak with the partners about construction claims in Bangladesh or across borders.
Book a consultation →















