Can a Performance Guarantee Be Stopped in Bangladesh? What Contractors Must Know

by Barrister Tahmidur Rahman | Oct 11, 2026 | Banking & Finance, Disputes & Public Law, Insights | 0 comments

Can a Performance Guarantee Be Stopped in Bangladesh? What Contractors Must Know

Summary. A performance guarantee is designed to give the project owner immediate payment security without requiring the owner to win the underlying construction dispute first. In Bangladesh, a contractor who wants to stop a demand faces a difficult distinction: the bank’s undertaking may be independent of the works contract, while the contractor’s strongest evidence may concern defective certification, delay or termination under that contract. Those points can matter later, but they do not automatically justify an injunction. The urgent questions are narrower: what exactly does the guarantee require, was a conforming demand made before expiry, and is there credible evidence of fraud in the demand or an exceptional risk of irretrievable injustice? This article explains the practical sequence for contractors, suppliers and sponsors as at 23 September 2026.

The commercial problem is simple to describe and expensive to manage. A project owner sends a demand to the issuing bank. The bank is preparing to pay. The contractor says the alleged default is false, the termination is wrongful, the payment certificate is disputed, or the owner owes the contractor more than the guarantee amount. The contractor asks a court to stop payment. The owner answers that the guarantee was given precisely to avoid waiting for that argument to be decided.

That conflict is not resolved by labelling the instrument a “performance bond”. The instrument’s text, its demand conditions, the issuing bank’s obligations, the governing law and the procedural route all matter. The analysis below separates the guarantee from the underlying project contract, identifies the limited circumstances in which urgent relief may be arguable, and explains what remains available if the bank has already paid.

The short answer: can a performance guarantee be stopped in Bangladesh?

Sometimes, but not merely because the contractor disputes the project owner’s case. A court may have power to grant interim protection. The Code of Civil Procedure, 1908 recognises temporary injunctions as supplemental relief and permits the court to make interlocutory orders to prevent the ends of justice being defeated.[1] Where an arbitration agreement is relevant, section 7A of the Arbitration Act, 2001 gives the court or, for international commercial arbitration, the High Court Division power to grant interim protective measures, including an interim injunction, subject to the Act.[2]

Those procedural powers do not turn every contractual disagreement into a basis for stopping a bank. A demand guarantee normally creates a separate payment obligation. The bank examines the guarantee and the demand, not the whole factual history of the works, unless the instrument itself makes payment conditional on specified proof. The beneficiary may therefore be able to obtain payment while the contractor’s claims for wrongful termination, unpaid certificates, extensions of time or defects remain for adjudication, arbitration or litigation.

The practical case for urgent relief usually has to be built around one or both of two exceptional ideas. First, there is clear, serious and particularised fraud connected with the demand or the beneficiary’s right to invoke the instrument. Second, refusing relief would create an exceptional and irretrievable injustice that cannot realistically be repaired through a later money judgment. The exact formulation and threshold are fact-sensitive. Bangladesh’s accessible primary statutes do not set out a standalone “bank guarantee fraud rule”; the position is developed through the instrument, general interim-relief law and judicial practice. A contractor should not assume that a general proposition from another common-law jurisdiction automatically decides a Bangladesh application.

Start with the instrument, not the project narrative

A performance guarantee is not one universal product. It may be an independent, irrevocable, unconditional demand undertaking; a conditional guarantee; a suretyship; an advance-payment guarantee; or a contractually described security that uses the word “guarantee” without clearly stating what the bank must see before paying. Calling it a guarantee does not answer the question.

The Contract Act, 1872 defines a “contract of guarantee” as a contract to perform the promise or discharge the liability of a third person in case of that person’s default. It identifies the guarantor as the surety, the defaulting party as the principal debtor, and the beneficiary as the creditor.[3] That statutory definition describes the relationship but does not, by itself, convert every bank instrument into an unconditional demand guarantee. The text signed by the bank is the starting point for identifying the actual obligation.

An independent demand guarantee generally contains language such as “irrevocably and unconditionally undertake to pay” a stated amount on the beneficiary’s written demand, sometimes accompanied by a declaration that the contractor has failed to perform. A conditional instrument may require a certificate, engineer’s determination, evidence of default, or another document. A guarantee may also require presentation at a named branch, in a specified form, before a stated date, with a claim reference or signature by an authorised officer.

The distinction is operational. If the bank must pay against a compliant demand, the contractor cannot ordinarily ask the bank to decide whether the owner correctly assessed delay, defects or entitlement. If the guarantee requires proof that has not been supplied, the contractor may have a stronger document-based objection. That objection is not necessarily “fraud”; it may be a failure to satisfy the instrument’s express conditions.

A useful way to frame the issue is in three columns:

Question What it concerns Why it matters urgently
What does the guarantee promise? The bank’s own undertaking Determines whether payment is documentary or merits-based
What must a demand contain? Conditions of presentation, certification and timing A defect may make the demand non-conforming
What happened under the project contract? Default, termination, valuation and counterclaims Usually belongs in the underlying dispute, not the bank’s first payment decision

TRW’s Bangladesh dispute-resolution overview similarly begins with the operative documents, the immediate time-sensitive decision, the procedural setting and the jurisdictions involved. That is particularly important where the instrument, project contract, bank and assets are in different countries.

Independence is the commercial point of the security

The independence principle means that the bank’s payment obligation is analysed separately from the underlying contract between owner and contractor. The bank is not normally a party to the engineering merits dispute. It has undertaken a payment obligation to the beneficiary on the terms written in the guarantee. The beneficiary’s demand may be wrong as a matter of contract and still appear facially compliant as a demand under the instrument.

This is why an owner can say, in substance, “pay first, argue later”. The contractor’s remedy is not necessarily lost. The contractor may pursue damages, restitution, a declaration, an account, or other relief under the project contract. But the existence of a possible later remedy is one reason a court may decline to interfere with a payment mechanism intended to be swift.

Independence is not absolute. It is bounded by the wording of the undertaking, applicable mandatory law, and recognised exceptions. The bank cannot rely on independence to pay a demand that plainly fails an express condition. Nor does independence protect a beneficiary who procures payment through a deliberately dishonest demand where the fraud is established with sufficiently strong evidence and is material to the call. The difficult question is proof, not the existence of the concept.

The contractor should therefore avoid a submission that says only: “The owner is wrong about the contract.” A more focused submission asks: “What exact statement did the owner make to the bank? Was it knowingly false? What documents show that falsity? Did the owner know the demand was not permitted? Does the instrument require a document that was absent or invalid? What irreversible harm would follow if payment is made?”

The answer may still be no. But those are the questions a court can assess without conducting a full trial on the project.

Why the underlying contract dispute may be insufficient

Consider a common sequence. The employer issues a notice alleging delay. The contractor disputes the notice and claims an extension of time. The employer terminates, calls the performance guarantee and says the contractor failed to perform. The contractor files an arbitration notice and seeks an injunction, arguing that termination was wrongful.

The contract dispute may be substantial. It may involve critical-path evidence, expert programming, design responsibility, access failures, variation valuation and allegations of prevention. Yet those issues usually require evidence and a merits process. If the guarantee requires only a written demand stating that the contractor is in default, a court may view the demand as the exercise of the independent security rather than a question to be decided by the bank.

Three distinctions are important.

A disputed default is not automatically fraud. A beneficiary can be wrong, overconfident or commercially aggressive without having made a dishonest demand. Fraud requires evidence of deliberate deception or a similarly serious abuse of the payment mechanism. A contractor’s affidavit asserting that the owner knew the call was unjustified will usually need supporting documents, admissions, chronology or other objective material.

A counterclaim is not automatically irretrievable injustice. The contractor may be owed unpaid work, variation amounts or delay damages exceeding the guarantee. That may support a monetary claim or set-off argument under the project contract. It does not necessarily show that payment of the guarantee cannot later be compensated or recovered.

Arbitration does not automatically suspend the guarantee. An arbitration clause determines the forum for the underlying dispute. It does not, without more, rewrite the bank’s promise or prevent a beneficiary from making a demand. The arbitration agreement and the guarantee should be analysed together, but they perform different functions.

This does not mean that a contractor should wait. It means the response should be targeted. If the owner’s demand is plainly outside the agreed amount, signed by an unauthorised person, sent after expiry, delivered to the wrong place, or unsupported by a document expressly required by the guarantee, the contractor may be dealing with a non-compliant demand. If the owner has fabricated a certificate or knowingly asserted a fact contradicted by its own contemporaneous records, the evidential picture may move towards fraud. Those are different cases from a normal disagreement over performance.

The narrow grounds for restraining payment

1. Non-compliance with the guarantee’s own terms

The first and often most concrete ground is documentary. Review whether the demand complies with every condition that the bank must apply. Typical questions include:

  • Was the demand received by the issuing bank or named branch in the permitted manner?
  • Was it received before the expiry date, including any time zone or banking-day wording?
  • Does it identify the guarantee number, contractor and project correctly?
  • Is it signed by the beneficiary or an authorised representative where required?
  • Does it contain the exact declaration or certificate required by the instrument?
  • Is the amount within the cap, and does the instrument permit partial or multiple demands?
  • Was an extension, amendment or reduction effective before the demand?
  • Does the guarantee say that a demand must be accompanied by an engineer’s certificate, an adjudicator’s decision, or evidence of a contractual notice?

The bank may not be required to resolve factual disputes embedded in a certificate. But a complete absence of a required document, an obvious mismatch, or a demand made outside the agreed mechanism can be materially different from an allegation that the beneficiary’s certificate is factually wrong.

2. Fraud connected with the demand

Fraud is an exceptional ground because it protects the integrity of the instrument without converting every disputed call into litigation about the works. The evidence must be more than suspicion. Useful material may include an internal owner document acknowledging that the alleged default did not occur; a contemporaneous admission that the demand is being used solely to obtain leverage; a forged or backdated certificate; an assertion that the owner knows is contradicted by a final acceptance document; or evidence that the beneficiary has deliberately concealed a condition that makes the call unavailable.

The fraud must be connected to the demand or the beneficiary’s entitlement to invoke the guarantee. A contractor should identify the precise representation made to the bank and explain why it was knowingly false or dishonest. Broad accusations against the owner, its engineers or project managers weaken the application if they are not tied to the call.

Evidence should be assembled in a way a judge can test quickly: the guarantee; the demand; the exact contractual clause; the relevant notice; the certificate or declaration; a dated chronology; the contradictory record; and a short witness explanation of how each document proves knowledge or dishonesty. Technical evidence may be important, but a lengthy project history is not a substitute for proof of fraud.

3. Exceptional irretrievable injustice

Courts may also consider whether payment would produce an exceptional harm that cannot be repaired by a later award or judgment. The threshold is high. Ordinary cash-flow pressure, loss of working capital, financing cost, reputational damage or the need to pursue recovery may not be enough. The contractor must explain why a later money remedy is practically incapable of restoring its position.

Examples sometimes advanced in common-law guarantee disputes include a beneficiary that is insolvent or beyond effective recovery, a payment that would trigger an irreversible state action, or a structure in which funds cannot realistically be recovered even if the contractor succeeds. Whether such circumstances satisfy a Bangladesh court depends on the evidence, the parties, available assets, forum and legal route. The point should be pleaded carefully as an exceptional consequence, not as a synonym for inconvenience.

A court may also balance the risk to the beneficiary if payment is stopped. A sponsor may need the security to finance completion or protect public funds. The contractor should be prepared to offer an undertaking or other security where procedurally appropriate. Interim relief is equitable and discretionary; a bare assertion that the owner can wait may not carry weight.

What to review in the first hours

The first response should be a document-control exercise, not an unstructured project meeting. Preserve the original guarantee, all amendments, extension letters, bank correspondence, counter-guarantees, the demand and proof of delivery. Obtain the bank’s actual receipt time if possible. Identify who is authorised to communicate with the bank and who may provide instructions to counsel.

Then build a short matrix:

Item Record to locate Immediate decision
Expiry Original instrument, extensions, amendment acknowledgements Has a valid demand arrived before expiry?
Demand Beneficiary letter, annexures, signature, delivery proof Does it comply on its face?
Trigger Contract clause, notice, certificate, termination letter Is the alleged trigger required by the guarantee?
Fraud Admissions, contradictory records, forged or backdated documents Is there particularised evidence, not just an assertion?
Forum Governing law, court clause, arbitration clause, bank location Where can urgent relief be sought?
Recovery Beneficiary identity, assets, insolvency indicators, security What is the realistic post-payment route?

Notify the bank without making careless admissions. Ask what documents it has received, what deadline applies, and whether its internal review can identify a documentary non-compliance. Do not assume that a bank’s willingness to pause voluntarily means it has accepted the contractor’s merits position. Equally, do not assume that a bank’s refusal to pause makes court relief impossible.

The issuing bank’s role matters. A contractor may have a separate relationship with the bank under an indemnity, facility, counter-guarantee or cash-margin arrangement. The bank may demand reimbursement from the contractor after paying the beneficiary. TRW’s banking and finance litigation practice page identifies guarantees, trade finance, payment instructions, recovery and cross-border enforcement as questions that turn on the product and governing documents. That is the right lens: the owner-bank relationship, bank-contractor relationship and project contract are connected commercially but not identical legally.

Guarantees are often lost or preserved by timing. Read the expiry clause literally. Some instruments expire on a fixed date. Some require the demand to be received by a named branch before close of business. Some contain a claim period after completion, a defects period or an automatic-extension mechanism. Some require the original guarantee to be returned, while others expire without return. A notice sent to the project office may not be a demand received by the issuing bank.

An extension letter should be checked for authority, effective date, revised amount and any changed demand wording. A contractor should not infer from negotiations that the guarantee has been extended. A beneficiary should not assume that a demand sent before expiry is valid if the instrument required receipt or a document that was only supplied later.

The Bangladesh Public Procurement Authority’s current official materials show why public-project wording must be read from the applicable tender document rather than from general commentary. The BPPA page lists the Public Procurement Rules 2008, amendments and Public Procurement Rules 2025 materials.[4] BPPA standard documents include prescribed performance-security forms and bank-guarantee language.[5] A public contract may therefore have a mandated form, a specific issuing-bank requirement, and a defined period linked to completion or defects liability. The contractor should identify the version incorporated into its tender and contract.

The existence of a 2025 procurement-rules page does not establish that every private or public guarantee follows the same wording. It also does not prove any supposed September 2026 change to the law. As at 23 September 2026, the safer approach is to verify the operative tender document, notice and applicable procurement rule for the particular procurement.

If the bank has already paid

Payment does not end the dispute. It changes it. The immediate “stop payment” question may become a recovery and preservation question against the beneficiary, and a reimbursement question between contractor and bank.

First, reserve rights under the underlying contract. A demand or payment should not be treated as an admission that the contractor defaulted. Send a carefully drafted notice identifying the contractual claims, without making inconsistent statements about the guarantee. Check notice, dispute-escalation and arbitration deadlines. A project contract may require a notice of claim within a short period even if the guarantee dispute is urgent.

Second, assess restitution or damages. If the demand was fraudulent, unauthorised or contractually unavailable, the contractor may consider relief requiring repayment, damages for breach, a declaration, an account, or interim asset-preservation measures. The cause of action and remedy depend on the guarantee, the project contract, the beneficiary’s conduct, governing law and the forum. Payment may also have triggered an indemnity or counter-indemnity under a bank facility; that document needs separate review.

Third, protect recoverability. Find out where the beneficiary is incorporated, where it banks, whether it has local assets and whether there is an insolvency or enforcement risk. A successful arbitration award is not the same as money in hand. The Arbitration Act’s interim-relief framework can matter before or during arbitration, but section 7A does not guarantee that a court will grant an injunction or order every remedy sought.[2]

Fourth, calculate the amount properly. The guarantee payment may be only one part of a larger account involving unpaid certificates, retention, advance-payment recovery, liquidated damages, variations and completion costs. Keep the guarantee payment in the chronology and accounting model. Do not double-count it as both security received and final proof of loss.

The Limitation Act, 1908 requires attention to filing periods and recognises written acknowledgment and part-payment provisions in its statutory scheme.[6] The applicable period depends on the cause of action and relief; the Act’s existence is not a basis for assuming a single limitation period for every guarantee or construction claim. Obtain a date-specific assessment promptly, especially where the beneficiary is outside Bangladesh or the contract selects a foreign forum.

Sponsors and beneficiaries: payment security is not a licence to overcall

The same discipline protects project sponsors. A beneficiary should verify the demand against the instrument before presenting it. It should preserve evidence of the alleged default and ensure that the signatory, certificate and delivery method comply with the guarantee. A demand designed only to pressure settlement creates avoidable injunction and recovery risk.

Sponsors should separate three decisions: whether the contractor defaulted; whether the guarantee permits a demand; and whether calling the guarantee is commercially and legally sensible. The first may involve the engineer and project team. The second is a document review. The third includes financing, completion and reputation considerations. A sponsor that confuses the three may present a demand that is strategically understandable but vulnerable on its own terms.

The bank should also be given clear, accurate documents. If the guarantee is independent, the beneficiary should not ask the bank to decide engineering merits. If the guarantee is conditional, the beneficiary should not omit the condition. Accuracy reduces the risk that a later court treats the demand as a dishonest attempt to obtain payment.

What to do next

If a demand is threatened or has arrived, assemble the guarantee, all amendments, the demand, the project contract, notices, certificates and a dated chronology immediately. Identify expiry, presentation mechanics, the issuing bank, the governing law and any arbitration clause. Then separate the possible arguments: documentary non-compliance, evidence of fraud, exceptional irretrievable harm, and the merits of the underlying contract claim.

Do not assume that a general dispute, an arbitration notice or a cash-flow emergency will stop payment. Do not assume that payment destroys the underlying claim. Each route depends on the documents, evidence, forum and timing. For a Bangladesh or cross-border matter, TRW’s contact route invites a non-confidential outline of the immediate decision; confidential or time-sensitive material should not be sent through an ordinary web form before an appropriate engagement is confirmed.

FAQs

1. Can a Bangladesh court stop payment under a performance guarantee?

It can have power to grant interim relief, including a temporary injunction, but relief is not automatic. The applicant normally needs a strong document-based case, particularised fraud or another exceptional basis, together with evidence addressing urgency and the consequences of payment. A dispute about the project contract alone may be insufficient.

2. Does an arbitration clause stop a bank from paying a guarantee?

No. An arbitration clause usually governs the underlying dispute between owner and contractor. It does not, by itself, suspend an independent guarantee or require the bank to decide the merits. The Arbitration Act, 2001 may support an application for interim protection, but the court will still assess the instrument, evidence and statutory conditions.

3. What evidence can show fraud in a guarantee demand?

The evidence should identify a material statement or document used in the demand and show why the beneficiary knew it was false or dishonest. Examples may include a forged certificate, an admission that the alleged default did not occur, or contemporaneous records contradicting a representation made to the bank. Suspicion, breach of contract or an honestly disputed assessment is not automatically fraud.

4. Can a demand be invalid because it was made after expiry?

Possibly, if the guarantee required receipt of the demand before a specified expiry date and the beneficiary failed to meet that condition. Check the exact wording, time zone, delivery route, extension documents and bank receipt record. A project-office notice or negotiation about extension is not necessarily a valid demand under the instrument.

5. What can a contractor do after the bank has paid?

The contractor can preserve its underlying contractual claims and assess recovery, restitution, damages, declarations and asset-preservation relief against the beneficiary. It should also review its bank indemnity or counter-guarantee, because payment may trigger reimbursement obligations. Limitation, notice and arbitration deadlines should be checked without delay.

6. Do Bangladesh public-procurement guarantees use a standard form?

Public-procurement documents may prescribe performance-security wording and an issuing-bank requirement. The BPPA publishes procurement rules and standard documents, including performance-security forms. The applicable tender and contract must be checked because the wording, expiry and presentation conditions can differ by procurement and document version.