Summary

The plaintiffs, the Master and the Chief Engineer of M.V. Crystal Gold, sued the vessel, her registered owner and her ISM and ship manager for wages unpaid from November 2014 until they signed off in 2015, claiming US$41,928.00 and US$30,896.66 respectively. The ship manager contested, denying jurisdiction and alleging that the plaintiffs stole stores, delayed cargo operations and caused losses, and that an inquiry had found them guilty. The defendants cross-examined the plaintiffs but led no evidence. The High Court Division held that the claim for seamen's wages fell within its Admiralty jurisdiction, that the plaintiffs proved their employment and unpaid wages by consistent oral and documentary evidence, and that continuing service after the fixed term was explained by the owners not relieving them. Pleadings and denied suggestions are not evidence, so the misconduct allegations remained unproved. A claim for seamen's wages is a maritime lien. The suit was decreed with costs and 6% interest, jointly and severally against the vessel, owner and manager.

Issues

  1. Q1

    Whether a claim by a Master and Chief Engineer for unpaid wages earned on board a vessel falls within the Admiralty jurisdiction of the High Court Division.

  2. Q2

    Whether the owners could withhold the wages on allegations of misconduct pleaded but not proved by evidence.

  3. Q3

    Whether a claim for seamen's wages constitutes a maritime lien against the vessel.

Key points

  • A claim for wages earned under contracts of employment as Master and Chief Engineer on board a vessel falls squarely within the Admiralty jurisdiction relating to seamen's wages.
  • Pleadings are not evidence, and suggestions put in cross-examination do not constitute proof unless accepted by the witness or otherwise established; pleas of estoppel, waiver and acquiescence must be proved by evidence.
  • Allegations of theft and misconduct pleaded in the written statement but not proved by any witness or document cannot justify withholding or forfeiting wages.
  • Where seamen remain on board after the contractual term because the owners did not arrange relief, and the owners prove no earlier cessation of service, wages remain payable for the period served.
  • A claim for seamen's wages is a privileged claim arising by operation of law, a classic maritime lien that travels with the vessel and is enforceable in rem.
  • The vessel, her registered owner and her ISM and ship manager are jointly and severally liable for the proved wages.

A maritime lien is a privileged claim upon a vessel arising by operation of law. A claim for seamen's wages is one of the classic categories of maritime lien. It travels with the vessel and may be enforced by an action in rem.

From the judgment, Justice Sikder Mahmudur Razi
The judgment

In the court’s own words.

Admiralty Suit 69/2015, as published by the Supreme Court of Bangladesh. 16 pages, with paragraph numbers for citing.

PDF
Call the Dhaka office+880 1708 000660WhatsApp · message usMessage our team
Message TRW on WhatsApp