Summary

The petitioner had a one-year agreement dated 13.08.2013 to market the respondent's Huawei products in Bangladesh, with Clause 29 requiring arbitration in Dhaka of all disputes arising out of or in connection with it. A later memorandum of understanding (MoU) dated 26.06.2014 promised rebates for meeting sales targets. The petitioner said it met the targets but was not paid. The respondent said the MoU was never signed or approved, contained no arbitration clause, and refused to appoint an arbitrator. The petitioner applied under section 12 of the Arbitration Act, 2001. The High Court Division held that arbitration clauses are construed liberally and that "in connection with" has wide meaning. The MoU, though unsigned, was prepared during the agreement, acknowledged in emails, partly acted upon, and its rebates depended on sales under the principal agreement, so the dispute was arbitrable under Clause 29. The application was allowed, the petitioner's nominee was appointed as arbitrator, and the respondent was directed to nominate its arbitrator within 30 days.

Issues

  1. Q1

    Whether a dispute over rebates under an unsigned memorandum of understanding, prepared during and linked to the performance of a principal agreement containing an arbitration clause, falls within that arbitration clause.

Key points

  • Arbitration clauses in commercial agreements are to be construed liberally to give effect to the parties' intention to arbitrate, and the phrase "in connection with" is not confined to disputes strictly within the agreement.
  • The unsigned MoU was prepared during the principal agreement, acknowledged in email correspondence and partly acted upon, and its rebates depended on sales targets under that agreement, so it could not be divorced from it.
  • Even if the MoU were treated as a separate understanding, its close nexus to the principal agreement made the arbitration clause applicable, having regard to section 9 of the Arbitration Act, 2001.
  • Where a later arrangement is intrinsically linked to a principal agreement with a valid arbitration clause and the parties acknowledged and acted on it, the clause covers disputes under it despite lack of formal execution.
  • The application under section 12 was allowed, the petitioner's nominee was appointed arbitrator and the respondent was directed to nominate its arbitrator within thirty days.

It is a settled principle that arbitration clauses in commercial agreements are to be construed liberally so as to give effect to the parties’ intention to arbitrate disputes.

From the judgment, Justice Md. Toufiq Inam
Law considered

Arbitration Act, 2001, section 12Arbitration Act, 2001, section 9

The judgment

In the court’s own words.

Arbitration Application 1/2019, as published by the Supreme Court of Bangladesh. 6 pages, with paragraph numbers for citing.

PDF
Call the Dhaka office+880 1708 000660WhatsApp · message usMessage our team
Message TRW on WhatsApp