Supreme Court Judgments, Summarised

by Barrister Tahmidur Rahman | Nov 3, 2026

Summary

A cable manufacturer supplying copper wire to the Bangladesh Rural Electrification Board furnished a performance bank guarantee of 10% of the contract value. After delivery was delayed, the Board's inspectors found the goods satisfactory without objecting to the delay, but the Board later decided to encash the guarantee and debarred the supplier for two years. The supplier applied to the District Judge, Dhaka under section 7A of the Arbitration Act, 2001 for an ad interim injunction, but the next date was fixed about four months later. It obtained a Rule in revision with an order of status quo, which the Appellate Division Judge-in-Chamber did not stay. The High Court Division found that, prima facie, the Board had not invoked clause 47 of the contract before acting, that the Nuvista Pharma principle on bank guarantees was not strictly attracted at the interlocutory stage, and that the delay breached clause 20 of the Civil Suits Manual. It continued the status quo and directed disposal of the injunction application within two months.

Issues

  1. Q1

    Whether the District Judge erred in fixing an application for ad interim injunction against encashment of a performance bank guarantee for hearing about four months later.

  2. Q2

    Whether the existing position should be preserved pending disposal of the injunction application where the employer invoked the guarantee without first using the contractual dispute resolution clause.

Key points

  • Interlocutory applications are urgent, and fixing the next date for an injunction application about four months after filing was inconsistent with clause 20 of the Manual of Practical Instructions for the Conduct of Civil Suits.
  • Where the employer, prima facie, did not invoke the contractual dispute resolution mechanism in clause 47 before invoking the performance bank guarantee, the order of status quo could not be said to be without lawful basis.
  • Although no fraud had been shown, the ratio in Nuvista Pharma Ltd. v Chairman, National Board of Revenue, 65 DLR (AD) 302 did not appear to be attracted in its strict application at the interlocutory stage, since the dispute raised whether the agreed contractual procedure was followed.
  • Gulf Air Company (GSC) v Travel Trade Ltd., 65 DLR (AD) 141 was distinguishable because the Rule was not disposed of summarily at the motion stage and the opposite party was fully heard.
  • The balance of convenience lay in maintaining the existing position until the District Judge decided the pending injunction application, which was directed to be disposed of within two months.

Accordingly for the ends of justice the order of status quo shall continue until disposal of Arbitration Miscellaneous Case Number 14 of 2026 by the District Judge.

From the judgment, Justice Md. Ali Reza
Law considered

Arbitration Act, 2001, section 7ACode of Civil Procedure, 1908, section 151Public Procurement Rules, 2008, rule 127(4)(c)Manual of Practical Instructions for the Conduct of Civil Suits, clause 20

The judgment

In the court’s own words.

Civil Revision 112/2026, as published by the Supreme Court of Bangladesh. 13 pages, with paragraph numbers for citing.