Projects / Construction & EPC
Construction and EPC contracts in Bangladesh
Public works in Bangladesh are tendered on e-GP under the Public Procurement Act 2006 and the 2025 Rules, while DFI and PPP projects often use FIDIC-based EPC terms. Claims, delay and disputes need early, careful handling.
Interactive · Approvals pathway
From concept to commercial operation
Each stage shows who acts, where, and the papers that move the project forward. Press play to watch the whole pathway, or tap any stage.
Interactive · Contract structure
Who signs what
The project company sits at the centre of a web of contracts. Tap a party to see its contract and why it matters to lenders.
Authorities and law
The people and rules that decide
The bodies you will deal with, and the laws and policies that frame the project.
Bangladesh Public Procurement Authority (BPPA)
Regulates public procurement, runs the e-GP system and administers the Review Panel; set up under a 2023 Act.
Procuring entities and HOPE
Ministries, departments and state bodies that tender, award and administer works contracts.
Review Panel
Independent appeal body hearing tenderer complaints after the administrative complaint stages are exhausted.
RAJUK and other development authorities
Approve building plans and land use within their areas, under building construction and town improvement laws.
Department of Environment
Issues site and environmental clearances under the Environment Conservation Rules 2023.
Commercial Courts and High Court Division
Hear construction and infrastructure contract disputes, arbitration applications and appeals.
Interactive · Risk cards
What goes wrong, and the fix
Tap a card to turn it over and see how sponsors and lenders usually manage the risk.
When it comes to a dispute
Where project disputes are decided
Most project contracts choose arbitration, but courts still matter for interim relief, enforcement and challenges to public decisions.
Procurement complaints and Review Panel
Tender-stage disputes about evaluation or award; complaint first to the procuring entity, then HOPE and Secretary, then appeal to the Review Panel.
Dispute board or engineer's determination
During performance, where the contract provides; a fast, interim decision on claims, variations and extensions of time that keeps work moving.
Arbitration
Final forum under most EPC and FIDIC-based contracts; Dhaka-seated arbitration falls under the Arbitration Act 2001, and DFI-funded contracts may provide a neutral seat.
Commercial Courts
Construction and infrastructure contract and tender disputes not referred to arbitration, plus arbitration-related applications, with pre-suit mediation where rules apply.
Questions sponsors ask first
Frequently asked questions
Is e-GP compulsory for public works tenders?
Yes. Under the Public Procurement Rules 2025, e-GP is mandatory for public procurement. A procuring entity without adequate ICT capacity may get BPPA approval to process tenders manually for a limited period. Foreign contractors should register early.
Are FIDIC contracts used in Bangladesh?
FIDIC-based conditions are common on DFI-funded and larger infrastructure contracts, often amended by particular conditions. Government-funded works usually use the standard tender documents issued under the procurement rules. Contractors should read the particular conditions closely.
Are liquidated damages enforceable?
Generally yes. Section 74 of the Contract Act 1872 allows reasonable compensation up to the stated sum without proof of actual loss, so the agreed rate acts as a ceiling. Clear drafting and good delay records matter.
Where are construction disputes heard?
Most EPC contracts provide for arbitration, with the courts supporting interim relief and enforcement. Since the Commercial Court Act 2026, construction and infrastructure disputes not sent to arbitration go to dedicated Commercial Courts.
Sources: Public Procurement (Amendment) Act 2026 (bdlaws) · Public Procurement (Amendment) Ordinance 2026 (bdlaws) · PPR 2025 takes effect (BPPA) · Formation of Review Panel (BPPA) · Commercial Court Act 2026 (bdlaws) · Arbitration Act 2001 (bdlaws) · Contract Act 1872, section 74 (bdlaws) · e-GP growth after PPR 2025 (BPPA)
Keep exploring
Related practice and sectors
Construction, EPC and O&M contracts
Practice areaConstruction claims and project disputes
Practice areaPublic procurement, bid strategy and tender documentation
Sector guidePower & energy projects in Bangladesh
Sector guideRenewable energy projects in Bangladesh
Sector guidePorts & logistics projects in Bangladesh
TRW & Co · Projects
Planning a project in Bangladesh?
TRW advises sponsors, lenders, contractors and investors on approvals, project contracts, finance and disputes. Tell us about the project and we will map the legal path.
General information as at November 2026, not legal advice. Laws, policies and figures change; check the current position before acting.