Construction and EPC contracts in Bangladesh

by Barrister Tahmidur Rahman | Nov 25, 2026

Projects / Construction & EPC

Construction and EPC contracts in Bangladesh

Public works in Bangladesh are tendered on e-GP under the Public Procurement Act 2006 and the 2025 Rules, while DFI and PPP projects often use FIDIC-based EPC terms. Claims, delay and disputes need early, careful handling.

Tk 3 lakh croreAnnual development programme, FY2026-27 · source
143,374Registered e-GP tenderers (Nov 2025) · source
8.5Average bids per tender, end 2025 · source

Interactive · Approvals pathway

From concept to commercial operation

Each stage shows who acts, where, and the papers that move the project forward. Press play to watch the whole pathway, or tap any stage.

Interactive · Contract structure

Who signs what

The project company sits at the centre of a web of contracts. Tap a party to see its contract and why it matters to lenders.

Authorities and law

The people and rules that decide

The bodies you will deal with, and the laws and policies that frame the project.

Bangladesh Public Procurement Authority (BPPA)

Regulates public procurement, runs the e-GP system and administers the Review Panel; set up under a 2023 Act.

Procuring entities and HOPE

Ministries, departments and state bodies that tender, award and administer works contracts.

Review Panel

Independent appeal body hearing tenderer complaints after the administrative complaint stages are exhausted.

RAJUK and other development authorities

Approve building plans and land use within their areas, under building construction and town improvement laws.

Department of Environment

Issues site and environmental clearances under the Environment Conservation Rules 2023.

Commercial Courts and High Court Division

Hear construction and infrastructure contract disputes, arbitration applications and appeals.

Public Procurement Act 2006Core statute for publicly funded goods, works and services; amended by Act 41 of 2026 with effect from 28 September 2025.
Public Procurement (Amendment) Ordinance 2026Further amendments issued 21 September 2026, in force from a date the government notifies; check status before bidding.
Public Procurement Rules 2025Replaced the 2008 Rules on 28 September 2025: mandatory e-GP, beneficial ownership disclosure, no works price cap, a Debarment Board.
Bangladesh Public Procurement Authority Act 2023Establishes BPPA to implement and oversee public procurement law and build procurement capacity.
Contract Act 1872, s 74Where a contract names a sum for breach, reasonable compensation up to that sum is recoverable without proof of actual loss.
Arbitration Act 2001Court interim measures (s 7A), setting aside within 60 days of receiving an award (s 42), and foreign award enforcement (s 45).
Commercial Court Act 2026Commercial Courts hear construction, infrastructure and tender disputes and arbitration matters; pre-suit mediation where rules apply; 60-day appeal.
Building Construction Act 1952Controls building construction and land use, sanction of plans and removal of unauthorised works; basis for the Bangladesh National Building Code.
Environment Conservation Rules 2023Classifies projects as green, yellow, orange or red and sets the procedure for location and environmental clearance certificates.

Interactive · Risk cards

What goes wrong, and the fix

Tap a card to turn it over and see how sponsors and lenders usually manage the risk.

When it comes to a dispute

Where project disputes are decided

Most project contracts choose arbitration, but courts still matter for interim relief, enforcement and challenges to public decisions.

01

Procurement complaints and Review Panel

Tender-stage disputes about evaluation or award; complaint first to the procuring entity, then HOPE and Secretary, then appeal to the Review Panel.

02

Dispute board or engineer's determination

During performance, where the contract provides; a fast, interim decision on claims, variations and extensions of time that keeps work moving.

03

Arbitration

Final forum under most EPC and FIDIC-based contracts; Dhaka-seated arbitration falls under the Arbitration Act 2001, and DFI-funded contracts may provide a neutral seat.

04

Commercial Courts

Construction and infrastructure contract and tender disputes not referred to arbitration, plus arbitration-related applications, with pre-suit mediation where rules apply.

Questions sponsors ask first

Frequently asked questions

Is e-GP compulsory for public works tenders?

Yes. Under the Public Procurement Rules 2025, e-GP is mandatory for public procurement. A procuring entity without adequate ICT capacity may get BPPA approval to process tenders manually for a limited period. Foreign contractors should register early.

Are FIDIC contracts used in Bangladesh?

FIDIC-based conditions are common on DFI-funded and larger infrastructure contracts, often amended by particular conditions. Government-funded works usually use the standard tender documents issued under the procurement rules. Contractors should read the particular conditions closely.

Are liquidated damages enforceable?

Generally yes. Section 74 of the Contract Act 1872 allows reasonable compensation up to the stated sum without proof of actual loss, so the agreed rate acts as a ceiling. Clear drafting and good delay records matter.

Where are construction disputes heard?

Most EPC contracts provide for arbitration, with the courts supporting interim relief and enforcement. Since the Commercial Court Act 2026, construction and infrastructure disputes not sent to arbitration go to dedicated Commercial Courts.

Sources: Public Procurement (Amendment) Act 2026 (bdlaws) · Public Procurement (Amendment) Ordinance 2026 (bdlaws) · PPR 2025 takes effect (BPPA) · Formation of Review Panel (BPPA) · Commercial Court Act 2026 (bdlaws) · Arbitration Act 2001 (bdlaws) · Contract Act 1872, section 74 (bdlaws) · e-GP growth after PPR 2025 (BPPA)

Keep exploring

Related practice and sectors

TRW & Co · Projects

Planning a project in Bangladesh?

TRW advises sponsors, lenders, contractors and investors on approvals, project contracts, finance and disputes. Tell us about the project and we will map the legal path.

General information as at November 2026, not legal advice. Laws, policies and figures change; check the current position before acting.