Projects / Power & energy
Power & energy projects in Bangladesh
Bangladesh has moved from negotiated, indemnified IPP deals to competitive tenders and merchant sales. We guide sponsors, lenders and contractors through tariffs, gas and LNG supply, grid access and the contracts that make power projects bankable.
Interactive · Approvals pathway
From concept to commercial operation
Each stage shows who acts, where, and the papers that move the project forward. Press play to watch the whole pathway, or tap any stage.
Interactive · Contract structure
Who signs what
The project company sits at the centre of a web of contracts. Tap a party to see its contract and why it matters to lenders.
Authorities and law
The people and rules that decide
The bodies you will deal with, and the laws and policies that frame the project.
Power Division (Ministry of Power, Energy and Mineral Resources)
Sets power sector policy, approves procurement and private generation models, and oversees state utilities.
Bangladesh Power Development Board (BPDB)
Single buyer and main offtaker; runs generation tenders and signs power purchase agreements with private producers.
Bangladesh Energy Regulatory Commission (BERC)
Issues energy licences, sets electricity and gas tariffs after public hearings, and resolves disputes between licensees.
Petrobangla
State oil, gas and mineral corporation; manages domestic gas supply and LNG imports through its subsidiaries.
Power Grid Bangladesh PLC (PGCB)
National transmission company; manages grid connection, high-voltage lines and dispatch data for generators.
Department of Environment (DoE)
Grants site and environmental clearance certificates under the Environment Conservation Rules 2023.
Invest Bangladesh
Apex investment agency under the Invest Bangladesh Act 2026, replacing BIDA, BEZA and the PPP Authority; handles registrations.
Interactive · Risk cards
What goes wrong, and the fix
Tap a card to turn it over and see how sponsors and lenders usually manage the risk.
When it comes to a dispute
Where project disputes are decided
Most project contracts choose arbitration, but courts still matter for interim relief, enforcement and challenges to public decisions.
International arbitration
Usual forum under PPAs and EPC contracts with foreign parties. Foreign awards are enforced under sections 45 and 46 of the Arbitration Act 2001.
BERC
Disputes between licensees, tariff questions and consumer complaints fall within the regulator's statutory jurisdiction under the BERC Act 2003.
Commercial courts
New specialist courts under the 2026 Act for commercial disputes, including construction and infrastructure contracts and tender matters.
High Court Division
Writ challenges to procurement decisions, permits or regulatory orders, applications to set aside domestic awards and interim relief in support of arbitration.
Questions sponsors ask first
Frequently asked questions
Can a private producer still sign a negotiated IPP deal?
The special provisions law that allowed negotiated awards was repealed in November 2024, and the repeal was confirmed by Parliament in 2026. New capacity is expected through competitive tenders or the merchant power model, under which producers sell to their own buyers and pay for grid use.
Who sets electricity tariffs?
BERC sets tariffs after a public hearing. The government power to set prices without a hearing, added in 2023, was removed by ordinance in August 2024 and the repeal was confirmed by an amending Act in 2026. Project tariffs under a PPA are fixed contractually.
Are existing IPP contracts still valid?
Yes. Repealing the 2010 law did not cancel contracts made under it, but the government retains authority to review them in the public interest, and several large agreements have been reviewed since 2024.
How is gas supplied to power plants?
Gas is supplied through Petrobangla group companies under the Bangladesh Gas Act 2010, which treats power as a separate consumer class. Domestic supply is falling, so a growing share comes from imported LNG under long-term and spot contracts.
Sources: Financial Express: Electricity and energy special provisions act repealed · UNB: JS passes 14 bills to convert ordinances into formal law (April 2026) · FAOLEX: Bangladesh Energy Regulatory Commission (Amendment) Act 2026 · Bangladesh Gas Act 2010 (bdlaws) · Dhaka Tribune: Power cuts persist despite record generation · Financial Express: LNG imports from long-term suppliers to rise 54pc in 2026 · Financial Express: Merchant power plant policy overthrows indemnified IPP regime · Invest Bangladesh Act 2026 (bdlaws)
Keep exploring
Related practice and sectors
Power & electricity projects
Practice areaLNG sales, regasification & cross-border gas infrastructure
Practice areaCross-border electricity interconnectors, power trading & grid access
Sector guideRenewable energy projects in Bangladesh
Sector guidePorts & logistics projects in Bangladesh
Sector guideEconomic zones & EPZs in Bangladesh
TRW & Co · Projects
Planning a project in Bangladesh?
TRW advises sponsors, lenders, contractors and investors on approvals, project contracts, finance and disputes. Tell us about the project and we will map the legal path.
General information as at November 2026, not legal advice. Laws, policies and figures change; check the current position before acting.