Summary

The petitioner won a tender in 2019 to build a Model Mosque and Cultural Centre in Batiaghata, Khulna. He said the land was acquired only on 26.11.2020, about 17 months after the agreement, needed soil-filling, and that the Covid-19 lockdown delayed the work. The authority cancelled the contract on 29.08.2023 and published a re-tender circular. The petitioner filed an arbitration case under section 12 of the Arbitration Act, 2001 and sought an interim injunction under section 7A to stop the re-tender, which the Senior District Judge, Khulna refused. In revision, the High Court Division found that a show cause notice dated 28.12.2022 had been issued and not answered, so the petitioner's claim of cancellation without notice showed he had not come with clean hands. The project served the public interest, a substantial part had already been built, and the loss could be compensated in money. The Rule was discharged, the status quo order vacated, and the District Judge directed to dispose of the arbitration case expeditiously.

Issues

  1. Q1

    Whether a contractor whose construction contract for a Model Mosque and Cultural Centre was cancelled was entitled to an interim injunction under section 7A of the Arbitration Act, 2001 restraining a re-tender of the project pending arbitration.

  2. Q2

    Whether the availability of monetary compensation as an equally efficacious relief defeated the claim of irreparable loss.

Key points

  • The petitioner's claim that the contract was cancelled without any show cause notice was misleading, since an unanswered notice dated 28.12.2022 was on record, and showed he had not come with clean hands.
  • The public interest would be adversely affected by any obstruction or delay in implementing the Model Mosque development project.
  • Where equally efficacious relief is available, the petitioner will not suffer irreparable loss if no injunction is granted, and here the breach of contract could be compensated by money.
  • The dispute arising from cancellation of the contract, including the petitioner's claim for money spent, could be settled in the pending Arbitration Miscellaneous Case.
  • The Court discharged the Rule without costs, affirmed the order refusing the injunction, vacated its status quo order and directed the District Judge, Khulna to dispose of the arbitration case expeditiously.

The public interest would be adversely affected if any obstruction or delay occurred in implementing the project.

From the judgment, Justice Jesmin Ara Begum
Law considered

Arbitration Act, 2001, section 7AArbitration Act, 2001, section 12Code of Civil Procedure, 1908, section 115(4)

The judgment

In the court’s own words.

Civil Revision 5836/2024, as published by the Supreme Court of Bangladesh. 8 pages, with paragraph numbers for citing.