Supreme Court Judgments, Summarised

by Barrister Tahmidur Rahman | Nov 3, 2026

Summary

The petitioner, owner of a rice mill, was accused of interfering with his electricity meter. Officials seized the meter, cut the supply and filed a case under sections 39A and 40A of the Electricity Act, 1910. A supplementary complaint claimed Tk. 96,57,403/- as compensation, and he was ordered to deposit Tk. 25,00,000/- or risk cancellation of bail. He argued the case was illegal because section 47 of the BERC Act, 2003 requires a written complaint by an officer authorised by the Commission. The High Court Division disagreed: section 47 covers only offences under the BERC Act, section 44 of that Act sends electricity theft to the 1910 Act, and section 50(3) of the 1910 Act lets a licensee's officer of at least Assistant Engineer rank file the case. An earlier writ rejected as not pressed did not create res judicata (a bar on relitigating decided matters). A Magistrate cannot recover the compensation claim or make its payment a bail condition. The Rule was discharged and the trial ordered to proceed.

Issues

  1. Q1

    Whether a case under sections 39A and 40A of the Electricity Act, 1910 is unlawful because it was not started by a written complaint from an officer authorised by the Bangladesh Energy Regulatory Commission under section 47 of the BERC Act, 2003.

  2. Q2

    Whether the writ petition was barred by res judicata because an earlier writ petition had been rejected as not pressed.

  3. Q3

    Whether a Magistrate trying an electricity theft case can assess or recover the electricity authority's compensation claim, or require its payment as a condition of bail.

Key points

  • The requirement of a written complaint by a BERC-authorised officer under section 47 of the BERC Act, 2003 is confined to offences under that Act and does not govern proceedings under sections 39A and 40A of the Electricity Act, 1910.
  • Section 50(3) of the Electricity Act, 1910 authorises an officer of the licensee not below the rank of Assistant Engineer to institute such a case, and the overriding effect in section 3 of the BERC Act, 2003 does not displace this, especially given section 48 of that Act.
  • An earlier writ petition rejected at the admission stage as not pressed, without any adjudication on the merits, does not bar a later writ petition by res judicata.
  • A compensation claim for lost electricity cannot be treated as a criminal fine, and a Magistrate has no authority under sections 39A or 40A to determine or recover it or to impose its payment as a condition of bail.
  • The Court left the legality and quantum of the Tk. 96,57,403/- claim open for the appropriate forum, discharged the Rule, vacated the interim order and directed the case to proceed expeditiously.

The power to grant or extend bail in a criminal proceeding cannot be exercised as a means of enforcing a disputed monetary claim which falls outside the scope of the Magistrate's statutory jurisdiction.

From the judgment, Justice Md. Toufiq Inam
Law considered

Bangladesh Energy Regulatory Commission Act, 2003, section 47Bangladesh Energy Regulatory Commission Act, 2003, section 44Bangladesh Energy Regulatory Commission Act, 2003, section 3Bangladesh Energy Regulatory Commission Act, 2003, section 48Electricity Act, 1910, section 39AElectricity Act, 1910, section 40AElectricity Act, 1910, section 50

The judgment

In the court’s own words.

Writ Petition 12861/2017, as published by the Supreme Court of Bangladesh. 10 pages, with paragraph numbers for citing.