Supreme Court Judgments, Summarised

by Barrister Tahmidur Rahman | Nov 3, 2026

Summary

A construction company had a 2021 contract with the Dhaka Electric Supply Company Limited (DESCO). Disputes arose over variation of works, payment, termination and encashment of the performance guarantee, which was encashed after the Appellate Division stayed an earlier status quo order. The company invoked section 12 of the Arbitration Act, 2001, and DESCO debarred it for two years under GCC Clause 95.1(d). The company challenged the debarment by writ, saying the Public Procurement Rules and contract procedures were not followed. The High Court Division said writ jurisdiction is not excluded just because a dispute arises from a contract, but it is not a forum for deciding disputed contractual claims. The contractual disputes belonged in the pending arbitration proceedings. Merely citing rules and clauses, without showing how mandatory requirements were breached, was not enough, and the petitioner had not shown the debarment was without jurisdiction or in breach of a mandatory statutory requirement. The Rule (the order to show cause) was discharged with no order as to costs.

Issues

  1. Q1

    Whether DESCO's decision to debar the petitioner contractor for two years under GCC Clause 95.1(d) called for interference under Article 102 of the Constitution.

  2. Q2

    Whether disputes over variation of works, termination, payment and encashment of the performance guarantee should be decided in writ proceedings when arbitration proceedings under the Arbitration Act, 2001 were pending.

Key points

  • A contractual relationship does not place every decision of a public authority beyond writ scrutiny, but Article 102 is not an alternative forum for deciding disputed contractual claims, particularly where the parties agreed to arbitration.
  • Allegations about variation orders, non-payment, wrongful encashment of the performance guarantee and consequential losses were matters more appropriately considered in the proceedings under the Arbitration Act, 2001.
  • The pendency of arbitration cannot by itself validate an otherwise unlawful administrative decision such as a debarment.
  • A mere reference to Rule 127 of the Public Procurement Rules, 2008, Rule 149 of the Public Procurement Rules, 2025 and contract clauses, without showing how their mandatory requirements were violated, does not establish a ground for interference.
  • The petitioner failed to show that the debarment was without jurisdiction or breached a mandatory statutory requirement, so the Rule was discharged without costs.

However, a mere reference to statutory provisions and contractual clauses, without demonstrating the precise manner in which their mandatory requirements have been violated, does not establish a ground for constitutional interference.

From the judgment, Justice Md. Toufiq Inam
Law considered

Constitution of the People's Republic of Bangladesh, Article 102Arbitration Act, 2001, section 12Public Procurement Rules, 2008, rule 127Public Procurement Rules, 2025, rule 149

The judgment

In the court’s own words.

Writ Petition 14137/2026, as published by the Supreme Court of Bangladesh. 9 pages, with paragraph numbers for citing.