Projects / PPP & transport
PPP and transport infrastructure in Bangladesh
Roads, bridges, elevated expressways, metro rail and airports can be delivered as PPPs. Since August 2026 the framework sits in the Invest Bangladesh Act 2026, which replaced the PPP Act 2015 and absorbed the PPP Authority.
Interactive · Approvals pathway
From concept to commercial operation
Each stage shows who acts, where, and the papers that move the project forward. Press play to watch the whole pathway, or tap any stage.
Interactive · Contract structure
Who signs what
The project company sits at the centre of a web of contracts. Tap a party to see its contract and why it matters to lenders.
Authorities and law
The people and rules that decide
The bodies you will deal with, and the laws and policies that frame the project.
Invest Bangladesh
Apex investment authority under the Prime Minister's Office; took over PPP Authority functions from 23 August 2026.
Cabinet Committee
Gives in-principle and final approval of PPP projects; small PPPs may be approved by the line ministry.
Finance Division, Ministry of Finance
Fiscal oversight of PPPs and management of viability gap and technical assistance financing.
Bangladesh Bridge Authority
Contracting body for major bridges, tunnels and elevated expressways under the Bangladesh Bridge Authority Act 2016.
Roads and Highways Department
Builds and manages national highways; sponsors road, bypass and toll road concessions.
Dhaka Mass Transit Company Limited
State company developing and operating Dhaka's metro rail lines under the Metro Rail Act 2015.
Civil Aviation Authority of Bangladesh
Airport owner, operator and aviation regulator; counterparty for airport terminal and operations concessions.
Interactive · Risk cards
What goes wrong, and the fix
Tap a card to turn it over and see how sponsors and lenders usually manage the risk.
When it comes to a dispute
Where project disputes are decided
Most project contracts choose arbitration, but courts still matter for interim relief, enforcement and challenges to public decisions.
Appeal to Invest Bangladesh
Bidders aggrieved by a contracting authority's order or decision during selection may appeal within 30 working days; the appeal decision is final.
Amicable settlement and neutral expert or mediator
Mandatory first tiers under s 42 before any court or arbitration; parties should build clear timetables into the PPP contract.
Arbitration
Final tier under s 42, seated in Dhaka, or another country by agreement in special cases. National or international rules may be adopted.
High Court Division and Commercial Courts
Interim measures and setting aside of international awards (Arbitration Act 2001), and enforcement or related commercial suits under the Commercial Court Act 2026.
Questions sponsors ask first
Frequently asked questions
Is the PPP Act 2015 still in force?
No. The Invest Bangladesh Act 2026 repealed it and dissolved the PPP Authority. Invest Bangladesh began work on 23 August 2026. Acts done under the old law are treated as done under the new Act, and the old authorities' contracts become Invest Bangladesh contracts.
Can we submit an unsolicited proposal?
Yes. Any private entity may submit an unsolicited proposal to build, rehabilitate and operate public infrastructure. It is evaluated under the relevant guidelines, so sponsors should check the current guideline before investing in studies.
What government support is available?
The Act allows technical assistance financing, viability gap financing, financing against equity and loans, financing of linked components and government guarantees. The amount and form are set in the PPP contract.
Can a PPP contract use English and foreign arbitration?
The contract may be written in the language the parties agree. Arbitration is seated in Dhaka by default, with another seat possible by agreement in special cases. National or international rules may be adopted.
Sources: Invest Bangladesh Act 2026 (bdlaws) · Bangladesh PPP Act 2015, marked repealed (bdlaws) · Invest Bangladesh begins journey as apex investment agency · PPP policies, rules and guidelines (PPP Office) · Dhaka Elevated Expressway project page (PPP Office) · Majority PPP projects stall (Financial Express, Feb 2026) · Metro rail sets record with 403,164 passengers (Financial Express) · Arbitration Act 2001 (bdlaws)
Keep exploring
Related practice and sectors
Infrastructure projects and PPP
Practice areaProject and infrastructure finance
Practice areaAviation regulation and airport projects
Sector guidePower & energy projects in Bangladesh
Sector guideRenewable energy projects in Bangladesh
Sector guidePorts & logistics projects in Bangladesh
TRW & Co · Projects
Planning a project in Bangladesh?
TRW advises sponsors, lenders, contractors and investors on approvals, project contracts, finance and disputes. Tell us about the project and we will map the legal path.
General information as at November 2026, not legal advice. Laws, policies and figures change; check the current position before acting.