Renewable energy projects in Bangladesh

by Barrister Tahmidur Rahman | Nov 25, 2026

Projects / Renewables

Renewable energy projects in Bangladesh

The Renewable Energy Policy 2025 targets 20% of power demand from renewables by 2030. Open tenders, merchant sales and net metering now replace negotiated deals. We advise sponsors, lenders and contractors on utility solar, wind and rooftop projects.

20%Renewables target by 2030 · source
1,563 MWRenewable capacity, June 2025 · source
8.27 US cents/kWhAverage open-bid solar tariff, 2025 · source

Interactive · Approvals pathway

From concept to commercial operation

Each stage shows who acts, where, and the papers that move the project forward. Press play to watch the whole pathway, or tap any stage.

Interactive · Contract structure

Who signs what

The project company sits at the centre of a web of contracts. Tap a party to see its contract and why it matters to lenders.

Authorities and law

The people and rules that decide

The bodies you will deal with, and the laws and policies that frame the project.

Sustainable and Renewable Energy Development Authority (SREDA)

Nodal renewable energy agency under the Power Division; prepares roadmaps, quality standards, purchase obligations and certificates.

Power Division

Owns the Renewable Energy Policy 2025, issues net metering and land guidelines and approves procurement models.

Bangladesh Power Development Board (BPDB)

Runs utility-scale solar tenders and signs 20-year power purchase agreements with winning bidders.

Bangladesh Energy Regulatory Commission (BERC)

Licenses generators and sets tariffs, including proposed tariffs and grid charges for renewable merchant plants.

Distribution utilities

Connect rooftop systems, install net meters and credit or pay for surplus power exported to the grid.

Invest Bangladesh

Apex investment agency under the Invest Bangladesh Act 2026; now administers PPP projects and investor registrations.

Department of Environment (DoE)

Issues site and environmental clearance for generation projects under the Environment Conservation Rules 2023.

Renewable Energy Policy 2025Targets 20% of demand from renewables by 2030; provides a 10-year corporate tax exemption, land allocation, purchase obligations and tradable certificates.
Sustainable and Renewable Energy Development Authority Act 2012 (Act 48 of 2012)Establishes SREDA and sets its functions; section 6 lists the Authority's responsibilities.
Net Metering Guidelines 2025Lets consumers export rooftop surplus to the grid. A 2026 incentive pays Tk 10.50 per unit for systems installed by February 2027.
Guidelines for Renewable Energy Projects on Government Land under PPP, 2026Lets agencies make unused land available for competitively procured projects, paid by lease, minority equity or both.
Bangladesh Energy Regulatory Commission Act 2003BERC licensing and tariff setting after public hearing; section 34A executive pricing power repealed by a 2026 amending Act.
Electricity Act 2018 (Act 7 of 2018)Sector framework including right of way, land acquisition for lines, licensee supply duties and dispute resolution.
Invest Bangladesh Act 2026 (Act 104 of 2026)Repealed the PPP Act 2015, BIDA Act 2016 and Economic Zones Act 2010; Chapter VIII now governs PPP approval and partner selection.
Environment Conservation Act 1995 and Environment Conservation Rules 2023Environmental clearance regime; the 2023 Rules replaced the 1997 Rules and set project categories and assessment requirements.
Arbitration Act 2001 (Act 1 of 2001)Sections 42 and 43 cover setting aside domestic awards; sections 45 and 46 cover enforcement of foreign awards.

Interactive · Risk cards

What goes wrong, and the fix

Tap a card to turn it over and see how sponsors and lenders usually manage the risk.

When it comes to a dispute

Where project disputes are decided

Most project contracts choose arbitration, but courts still matter for interim relief, enforcement and challenges to public decisions.

01

International arbitration

Usual forum for PPAs, EPC contracts and supply contracts with foreign parties; foreign awards enforced under sections 45 and 46 of the Arbitration Act 2001.

02

BERC

Licence matters, tariff decisions and disputes between licensees, including grid access and charges for merchant renewable plants.

03

Commercial courts

Specialist courts under the 2026 Act for commercial disputes, including construction and infrastructure contracts and tenders.

04

High Court Division

Writ challenges to tender decisions, permits and regulatory orders, and applications concerning domestic arbitral awards.

Questions sponsors ask first

Frequently asked questions

What does the Renewable Energy Policy 2025 offer investors?

It targets at least 20% of demand from renewables by 2030, offers a 10-year corporate tax exemption followed by five years of partial exemption, opens government land for projects and introduces purchase obligations and tradable renewable energy certificates.

Does BPDB give a sovereign guarantee on solar tenders?

Not in recent rounds. Weak response to the 5,238 MW tender in 2024 and 2025 was widely attributed to the lack of guarantees. The 2026 tender offered a 20-year PPA with full offtake as the alternative assurance.

Can a factory buy renewable power directly?

Yes. Since late 2024 private producers may sell directly to consumers and distributors through the grid, paying for its use. BERC is setting tariffs and charges for renewable merchant plants, so check the latest decisions before signing.

How does rooftop net metering work?

Under the Net Metering Guidelines 2025, consumers can install rooftop or on-site systems and export surplus to the grid. A 2026 incentive pays Tk 10.50 per unit for qualifying systems installed by 28 February 2027, running until February 2030.

Sources: Daily Star: Govt unveils new renewable energy policy · Financial Express: Govt announces special incentive package for rooftop solar power · TBS: BPDB now floats 495MW solar tenders after mega round falters · TBS: Solar tariff, open bidding slashes rates of new projects · Daily Star: PPP guidelines rolled out to use public land for renewables · Financial Express: BERC panel proposes Tk 6.48 solar power tariff for MPPs · SREDA Act 2012 (bdlaws) · Invest Bangladesh Act 2026 (bdlaws)

Keep exploring

Related practice and sectors

TRW & Co · Projects

Planning a project in Bangladesh?

TRW advises sponsors, lenders, contractors and investors on approvals, project contracts, finance and disputes. Tell us about the project and we will map the legal path.

General information as at November 2026, not legal advice. Laws, policies and figures change; check the current position before acting.