Appellate Division
Bangladesh v Bangladesh Paribesh Andolon (BAPA) and another
Civil Appeal 32/2005 · Decided 16 August 2022
An environmental organisation challenged construction of residences for the Speaker and Deputy Speaker within the National Assembly Complex designed by Louis Kahn, arguing that it breached Kahn's 1973 Master Plan, which showed the site as open green space, and lacked sanction under building laws. The High Court Division made the Rule absolute (granted the challenge). On the Government's appeal, the Appellate Division found that Kahn produced several master plans over time, earlier ones including a Speaker's house, so his plan was flexible. The project had been cleared by the Department of Architecture, approved by the Prime Minister by a memo of 27.04.1998 and reflected in a 2002 Master Plan, and neither the memo nor that plan had been challenged. The High Court Division had not shown environmental harm. Under section 3 of the Government Building Act, 1899, public buildings on government land are exempt from municipal building laws, and construction was completed under a stay. The appeal was allowed and the High Court Division's judgment set aside.
Appeal allowed; High Court Division judgment set aside
- High Court Division (HCD)The lower of the two Divisions of the Supreme Court of Bangladesh, which hears writs, appeals, revisions, bail matters and some original cases.Read the full explanation →
- Set asideTo cancel an earlier court order, decree, award, sale or conviction so that it no longer has legal effect, usually by a higher court or by the same court on a proper application.Read the full explanation →
- Q1
Whether construction of the residences of the Speaker and the Deputy Speaker within the National Assembly Complex was unlawful as a breach of Louis Kahn's Master Plan of 1973.
- Q2
Whether the Town Improvement Act, 1953 and the Building Construction Act, 1952 applied to construction of these residences on government land for a public purpose.
- Q3
Whether the writ petition could succeed when the approving memo of 27.04.1998 and the 2002 Master Plan were not challenged.
- Louis Kahn did not furnish a single master plan but submitted sets of plans from time to time, several including the Speaker's house, so the 1973 Master Plan was not an unamendable scripture.
- The construction was not arbitrary but was done with the approval of the Department of Architecture and the Prime Minister, and the High Court Division erred in failing to consider this.
- Since the memo dated 27.04.1998 and the latest Master Plan of May 2002 were not impugned in the writ petition, the Rule was liable to be discharged.
- Under section 3 of the Government Building Act, 1899, the residences, being for a public purpose on government land, were exempt from the Town Improvement Act, 1953 and the Building Construction Act, 1952.
- The High Court Division did not show how the environment was affected and ignored that construction was fully completed during the stay, so its judgment was set aside and the appeal allowed.
the said construction of residences of the Speaker and the Deputy Speaker being for the public purpose in the government land is exempted from complying with provisions of other municipal laws.
In the court’s own words.
Civil Appeal 32/2005, as published by the Supreme Court of Bangladesh. 22 pages, with paragraph numbers for citing.
1IN THE SUPREME COURT OF BANGLADESH
2APPELLATE DIVISION
3Present:
4Mr. Justice Hasan Foez Siddique, Chief Justice
5Mr. Justice Obaidul Hassan
6Mr. Justice M. Enayetur Rahim
7CIVIL APPEAL NO.32 OF 2005 (From the judgment and order dated 21.06.2004 passed by the High Court Division in Writ Petition No.3548 of 2003)
8Bangladesh and others ……..….Appellants
9-VersusBangladesh Paribesh Andolon (BAPA) .…..…Respondents and another For the appellants : Mr. Sk. Md. Morshed, Additional Attorney
10General with Mr. Sayem Mohammad Murad,
11Assistant Attorney General, instructed by Mr.
12Haridas Paul, Advocate-on-Record. For the respondents : Mr.Tanjib-ul-Alam, senior Advocate, instructed
13by Ms. Madhumalti Chy. Barua, Advocate-on-
14Record.
15Date of hearing : The 2nd and 3rd day of August, 2022. Date of judgment : The 16th day of August, 2022.
16JUDGMENT Obaidul Hassan, J. This Civil Appeal by leave granting order dated 10.11.2004 in Civil Petition for Leave to Appeal No.983 of 2004 at the instance of the appellants has been directed against the judgment and order dated 21.06.2004 passed by a Division Bench of the High Court Division in Writ Petition No.3548 of 2003 making the Rule absolute.
17The brief facts as has been narrated in the Writ Petition are that, in June 1959 the Central Government of Pakistan decided to establish two capitals in Pakistan, one each for the then East Pakistan and West Pakistan and the legislative capital was to be in Dhaka, Bangladesh (Erstwhile East Pakistan) and the idea of designing a new Assembly Building was taken up because Dhaka did not have an existing
18=2= structure to accommodate its new status as a ‘Second Capital’. World acclaimed famous architect Louis Isadore Kahn was opted for designing the National Assembly construction project and accordingly he received the commission for the project in the year 1962 and continued working on it till the last days of his life in 1974. The construction of the National Assembly Complex was finally completed in the year 1983 under the supervision of one of Louis Kahn’s associates. The National Assembly Complex is treated as the climax of the lifelong thinking of Louis Kahn about architecture, city and humanity. The aesthetic composition, visual clarity, spatial order and virtuoso engineering of the National Assembly Complex have been analyzed and studied by both the academics as well as students of architecture all over the world. The final Master Plan prepared by Louis Kahn in 1973 clearly lays out the structural composition of the buildings, including residences, plazas, fields, lakes, gardens and recreational facilities within the National Assembly Complex. However, the National Assembly Complex is continuously and incrementally being endangered and threatened by encroachment and construction of various buildings by the public authorities. The respondent No.1 is carrying out work on construction of the residences of the Speaker and Deputy Speaker (shortly the impugned project) within the National Assembly Complex in violation of the Louis Kahn’s Master Plan, 1973 causing irreparable damage to the form and beauty of the composition as envisaged by the original
19=3= Master Plan. The impugned project was first approved by the Speaker of the Seventh Parliament, Humayun Rashid Chowdhury but the then Prime Minister’s Office scrapped the impugned project in the face of strong public protest from the civil society, architectural community, environmentalists and the media. The present government revived the impugned project on the suggestion of some ill-motivated officials that Louis I. Kahn’s original plan envisaged such residences of the Speaker and the Deputy Speaker. The Master Plan, 1973 clearly shows that the land on which the impugned project is being built was meant to be open space with green fields.
20In the face of strong public protest the government had postponed the impugned project. However, after about a two month’s suspension of the work on the impugned project construction work had been restarted and with a view to finishing of the project quickly before facing further protest additional workforce, working extra hours has been engaged in order to complete the construction of residential units for the Speaker and Deputy Speaker.
21The impugned project being undertaken in violation of Louis I. Kahn’s Master Plan, 1973 the Respondents filed the Writ Petition No.3548 of 2003 before the High Court Division. A Rule was issued on the respondents’ prayer for a declaration that the impugned project has been undertaken without lawful authority and is of no legal effect and unconstitutional as being done in violation of the law and fundamental rights of the respondents as guaranteed under
22=4= Articles 27, 31 and 32 of the Constitution and a direction was sought upon the writ respondent No.2 to declare the National Assembly Complex as National Heritage Site with a further direction upon the Writ Respondents to apply to the UNESCO to declare the Bangladesh National Assembly Complex as a World Heritage Site. There was also a prayer for an injunction restraining the Writ Respondents from carrying out any further construction of the impugned project.
23The writ respondent No.1 filed an affidavit-in-opposition denying the allegations of the writ petitioners contending inter alia that there are Master Plans dated 12th March, 1962, 3rd May 1963, 21st December 1963, 10th May 1964, August 1964 and February 1965 wherein the Speaker’s House was incorporated. The latest Master Plan for the Shangshad Bhaban area was formally approved on May, 2002 by the Ministry of Housing and Public Works. It was further claimed that the Department of Environment and RAJUK are not the germane body to call in question where construction is made on the government land rather the Public Works Department is the competent body to embark on construction work of the buildings on the government land on obtaining endorsement from the Department of Architecture. Referring an excerpt from David Wisdom’s write-up “Kahn’s Building at Dhaka” it was further contended that Kahn’s Master Plan is not an unyielding document, but it is supple and there had been insertions and eliminations in his plan. It was also stated that Kahn died before the preliminary design was entirely finished.
24=5= He frequently changed the shapes and positions in the plan with his own reasons without any pressure from the government to get on with these designs. Kahn also studied the special houses for the President, the Speaker and the Deputy Speaker and he enjoyed those kind of work so much under no pressure to show progresses that every time he submitted a sketch for any one of them. There was a radical change of design from the previous submission. Finally the decision came not to build the three houses. Again, quoting an extract from the book titled “The Story of Ayub Nagar: Decade of Development and Reforms: 1958-1968” published by the Department of Film and Publication, Dhaka under the heading “South Elevation of Speaker’s Resident” it was also stated that construction of the Speaker and the Deputy Speaker’s residence in the legislative enclave has been an integral part of the government approved plan and both the residences are within the residential block of National Assembly which were built under Louis Kahn’s direct supervision, will not in any way jeopardize and blemish the beauty and grace of the National Assembly Complex. It was further contended that Louis Kahn designed and made construction of the residential block of the National Assembly Complex under his direct supervision. These buildings were not shown in his own Master Plan of 1973. Louis Kahn did not furnish any unique master plan but he submitted sets of master plans from time to time. It is a co-incidence that Louis Kahn died in 1974 and no further Master Plan could be produced by him. It
25=6= was also contended that the Secretary, Ministry of Housing and Public Works placed a summary to the then Prime Minister on 09.08.1998 regarding the construction of Speaker and Deputy Speaker’s House within the residential block of the National Assembly and the then Prime Minister accorded approval of the said construction taking into consideration about the architectural elegance of the open space of the National Assembly Complex. It was also stated that the present construction is being made in similitude with the other buildings constructed at the supervision of Louis Khan himself. The symbolic value of the green fields of the National Assembly from the context of the new structure shall in no way tarnish the symbolizing effect of the landscape of Bangladesh and in fact the construction of residences of Speaker and Deputy Speaker will not any way mutilate and distort the beauty of the green area. It was further contended that The Town Improvement Act, 1953 and Building Construction Act, 1952 have no relevance with the construction of the residences for the Speaker and the Deputy Speaker which are being constructed on government’s own land after obtaining clearance from the Department of Architecture and on approval of the Prime Minister, the Chief Executive of the Government while the Town Improvement Act, 1953 and Building Construction Act, 1952 are applicable in cases of construction of building on private land. It was further contended that on the basis of the Government Order dated 27.04.1998 for construction of
26=7= residences of the Speaker and the Deputy Speaker a Master Plan for the said purpose has been approved in the place as stated in memo dated 27.04.1998 but the Memo dated 27.04.1998 and Master Plan having not being impugned, the Writ Petition is misconceived and not maintainable.
27In reply the writ petitioners filed an affidavit controverting all the statements made in the affidavit-in-opposition filed by the writ respondents and stated that the Master Plan of 1973 prepared and finalized by Louis Kahn superseded and replaced the initial plans prepared in 1962, 12 March 1963, 3 May 1963, 21 December 1963, 10 May 1964, August 1964 and February 1965. Louis Kahn was initially commissioned to design the plan for an entire site for a city which was meant to be the Second Capital of Pakistan. The design for National Assembly Complex is only a component of the larger design of the entire capital site containing plans for a Supreme Court, a hospital, a library, a mosque, a museum, schools, clubs, markets, offices, recreational areas, special diplomatic enclave and low and high income residential areas. It was the Pakistan Government, prior to the independence of Bangladesh, which had contemplated the construction of the houses of the Speaker and Deputy Speaker as temporary residence as ancillary facilities for the second capital. However, after 1971, with the emergence of Bangladesh as an independent state, Louis Kahn was commissioned to set up the plan for the Assembly Complex of Bangladesh which was to serve quite a
28=8= different role to that of an Assembly building for a second capital. It was in these changed circumstances that Louis Kahn drew up the final Master plan of 1973 which clearly did not have any residential buildings in the Legislative Enclave of the plan. The alleged latest Master Plan for the Shangshad Bhaban area as prepared by the Ministry of Housing and Public Works in May 2002 defaces and destroys the symmetry of the National Assembly Complex Buildings as prepared and envisioned by Louis Kahn. It was stated further that the issuance of the circular from the Ministry of Housing and Public Works dated 16.3.1999 is ex facie without lawful authority and is in violation of the Rules of Business, Town Improvement Act, 1953, Building Construction Act, 1952 and gnvbMix, wefvMxq kni I †Rjv kn‡ii †cŠi GjvKv mn †`‡ki mKj †cŠi GjvKvi †Ljvi gvV, Db¥y³ ¯’vb, D`¨vb Ges cÖvK…wZK Rjvavi msiÿ‡Yi Rb¨ cÖYxZ AvBb, 2000. It was lastly contended that despite the Government is under a duty to adopt measures for the protection against disfigurement, damage of all monuments, objects or places of special artistic or historic importance or interest as per Article 24 of the Constitution, it has violated the provisions of the Constitution.
29The High Court Division upon hearing both sides made the Rule absolute by the impugned judgment and order dated 21.06.2004.
30Feeling aggrieved with the judgment and order dated 21.06.2004 passed by the High Court Division in Writ Petition No.3548 of 2003 the writ respondents-appellants filed the Civil Petition for Leave to Appeal No.983 of 2004 before this Division and
31=9= after hearing the parties this Division was pleased to grant leave by order dated 10.11.2004 and hence the instant Civil Appeal.
32Mr. Sk. Md. Morshed, the learned Additional Attorney General along with Mr. Sayem Mohammad Murad, the Assistant Attorney General appearing for the appellants took us through the judgment and order dated 21.06.2004 of the High Court Division, the materials on record and submitted that the High Court Division committed error of law in not taking into consideration that (a) the construction is made on government land by Public Works Department after obtaining clearance from the Department of Architecture and (b) on the basis of the Government Order dated 27.04.1998 for construction of residences of the Speaker and the Deputy Speaker, a Master Plan for such construction has been approved in the year 2002 in the place and (c) the said memo dated 27.04.1998 and the Master Plan having not been impugned, the rule in the Writ Petition was liable to be discharged. The learned Counsel contended next that the High Court Division committed error of law in not holding that the Town Improvement Act, 1953 and the Building Construction Act, have no relevance with the present construction work which is being done on government land after taking clearance from the Department of Architecture and on approval of the Prime Minister, the head of the government whereas the aforementioned laws are applicable in case of construction on the private land. Assailing the impugned judgment of the High Court Division the learned Counsel submitted
33=10= further that the High Court Division committed error of law in making the Rule absolute without giving any specific finding as to how the impugned construction work caused environmental hazard affecting the fundamental rights of the public or of the writ petitioners. The learned Counsel contended further that the High Court Division committed illegality as it did not take into consideration that the construction of residences within the National Assembly Complex for the Speaker and the Deputy Speaker, who hold an exalted position under the Constitution are state necessity and for public interest. The learned Additional Attorney General finally submitted that during the stay of the judgment and order of the High Court Division by this Division 100% of the impugned construction work has been completed, but the High Court Division without taking into consideration committed error of law by passing the impugned judgment and order, which is liable to be set aside.
34Conversely, Mr. Tanjib-ul Alam, the learned senior Advocate for the respondents vehemently opposed the submissions made by the learned Additional Attorney General. The learned Counsel for the respondents contended that the impugned construction work is illegal and without lawful authority since no sanction has been taken from the appropriate authority under the Building Construction Act, 1952. The learned Counsel for the respondents next submitted that by converting the open space for the National Assembly Complex into residential building for the Speaker and the Deputy Speaker, the
35=11= government has violated the fundamental right of the respondents due to the reason that protection of the environment is considered to be part of the fundamental right to life. The learned Counsel contended next that the impugned construction project being done flouting the Master Plan, 1973 of the National Assembly Complex prepared by the world renowned architect Louis Kahn will tarnish the architectural beauty of the National Assembly Complex. The learned Counsel, in fine, craved for dismissal of appeal having no merit for consideration.
36We have considered the submissions of the learned Advocates for the both sides, perused the judgment and order dated 21.06.2004 passed by the High Court Division in Writ Petition No.3548 of 2003 and the materials on record.
37It is admitted that Louis Kahn is recognized worldwide as one of the greatest architects of the twentieth century and the National Assembly Complex is an architectural masterpiece created by him. The timeless quality of the building transcends the boundary of the architecture and reaches out not only to our minds but to our visions of hopes. The architect’s key design philosophy was to represent Bengali culture and heritage, while at the same time optimizing the use of space.
38At this juncture, it is pertinent to know whether Louis Kahn had a unique Master Plan of the National Assembly Complex and the
39=12= Speaker and the Deputy Speaker’s residence was included in that plan. From the record it appears that Louis Kahn did not furnish any unique master plan but he submitted sets of Master Plan from time to time. There are Master Plans of the year 1962, March 12, 1963, May 3, 1963, December 21, 1963, May 10, 1964, August 1964, February 1965 and the Speaker’s house was included in those plans. It is a coincidence that Louis Khan died in 1974 and no further Master plan could be produced by him.
40Now, let’s have a glimpse on a relevant extract of David Wisdom’s write-up “Kahn’s Building at Dhaka”-
41“Kahn died before the preliminary design was entirely
42finished. Kahn studied the architectural composition and
43site placement of the Supreme Court, the Central
44Government Library and the mosque. He frequently
45changed the shapes and positions with his own reasons
46but there was no pressure from the Government to get on
47with these designs. No real preliminary plans were
48formally submitted and these projects are not shown on
49Kahn’s last Master Plan. Kahn also studied the special
50houses for the President, the Speaker and the Deputy
51Speaker, he enjoyed these kind of work so much under no
52pressure to show progresses that every time he submitted
53a sketch for any one of them. There was a radical change
54of design from the previous submission. Finally the
55decision came not to build the three houses. When Kahn
56received his commission from Bangladesh these houses
57were not included.”
58=13=
59Further, “The Story of Ayub Nagar: Decade of Development and Reforms 1958-1968” published by the Department of Film and Publication, Dhaka under the heading “South Elevation of Speaker’s Resident” reads as follows-
60“The residences of the Speaker and the Deputy Speaker of
61the National Assembly:
62Provision has been made for construction of the
63residences for the Speaker and one Deputy Speaker in the
64Legislative Enclave at an estimated cost of 8 Lakh. These
65residences are also scheduled to be completed within the
66current plan period.”
67From the above it is clear that the construction of the Speaker and the Deputy Speaker’s residence in the National Assembly Complex has been an integral part of the government approved plan. The construction of the Speaker and the Deputy Speaker’s residence are within the residential block of National Assembly Complex which built under Louis Kahn’s direct supervision, will not in any way deface the aesthetic value and grace of the National Assembly Complex.
68The Master Plan of 1973 provided for the building of five sectors of establishments namely: (a) Assembly Sector, (b) Secretarial Sector, (c) Civic Sector, (d) Housing Sector and (e) Hospital Sector. Within the Assembly Sector Louis Kahn’s 1973 Master plan catered for (1) Fountain Drive and Promenade, leading to Sher-E-Bangla
69=14= Nagar Gate, (2) Crescent Lake, (3) Recreation Garden and Court, (4) Recreation Building, (5) Arcades, (6) Cricket Field, (7) Hostels for Secretaries, (8) Hostels for Ministers, (9) Lake, (10) Presidential Plaza, (11) National Assembly, (13) Memorial Mazar, (14) Garden
70(15) Cooling Tower, (16) South Plaza, (17) Fountain and Drainage Canal, (18) Arcaded Garden Courts, (19) Hospitality Hall and (20) Servant’s Quarters. Amongst these various types of establishments within Sher-E-Bangla Nagar there are various Sectors and within the Assembly Sector which is absolutely the government domain as apparent from the Master Plan of 1973, the government opted to erect buildings for the Speaker and the Deputy Speaker, who are provided a unique position under the Constitution and such offices are basically referring to two institutions rather than two individual persons. Thus, the construction of the two residences has been undertaken due to pragmatic situation, state necessity and public interest. As such there is no hard and fast rule as to stick to the Master Plan of 1973 of Louis Kahn and treat it as an unamenable scripture rather it is supple which underwent changes from time to time as written by David Wisdom on Kahn’s Building at Dhaka.
71On the other hand, the Department of Architecture is the only Government organization to impart architectural services under the Ministry of Housing and Public Works and responsible for designing all Government buildings and also for public housing
72=15= schemes across the country. The Department not only prepares architectural designs and layout plans for public building and housing projects, but also advises the government on policy matters relating to human settlement and land use planning.
73All the architectural drawings of projects implemented for different Ministries, which are executed by the Public Works Department and National Housing Authority are prepared by the Department of Architecture. Besides providing the services and help of architecture, planning and housing design for the public sector the Department of Architecture played a vital role during the formulation of the National Housing Policy,1993 and the National Building Code 1993 (Modified in 1999). The steering Committee constituted by the Government to update the Building Code is also headed by the Chief Architect of this Department. The Chief Architect of this department has been declared as ex officio “Authorized Officer” under the Building Construction Act, for all public building and projects implemented under the Ministry of Housing and Public works.
74The functions of the Department of Architecture are enumerated in the following-
75a. Basic architectural services including site selection,
76preliminary survey of sites before taking up planning and
77designing of building project;
78=16=
79b. Preparation of detailed drawings for execution of building
80projects and supervision of construction work to ensure
81execution as per Architects plans and specification;
82c. Preparation of Master plans and Lay out plans;
83d. Studies proposals for formulation of space standards for
84Government offices and residential buildings and assessing
85land requirements for various building projects;
86e. Offer advice to Government on policy matters relating to
87human settlement and land use planning;
88f. Assisting various public agencies in preparing plans for their
89building projects including assessing their land requirement.
90[Source: http://www.architecture.gov.bd/site/page/64fdbcba-
91828f-4855-822f-ec6e672e937f/-].
92It is evident from the above discussion that the Department of Architecture is concerned with the architectural value of the National Assembly Complex and in the present case the government has not unilaterally and with arbitrary manner taken the decision of construction of the present construction work rather the same is done with the approval of the Department of Architecture and in the way the government complied with the legal requirement, but the High Court Division could not take the matter into consideration, therefore, committed illegality in making the Rule absolute.
93From the record it is seen that the secretary, Ministry of Housing and Public Works placed a summary to the then Prime
94=17= Minister on 09.8.1998 and the then Prime Minister approved 1.37 acres of land by the side of National Assembly Road through Memo No.P.C./IM-803/97(Part-1)49 dated 27.04.1998 (Annexure-5). Subsequently as per direction of the then Prime minister the design and structure of the residences of the Speaker and the Deputy Speaker was prepared and the said structural maps have been approved. Thus a latest Master Plan (Annexure-1) for the National Assembly Complex was formally approved in May 2002. But the said Memo dated 27.04.1998 (Annexure-5) and the latest Master Plan (Annexure-1) having not been impugned in the Writ Petition, thus the Rule issued in the said Writ Petition was liable to be discharged.
95It transpires from the Memo dated 09.08.1998 (Annexure-4) that the then Prime Minister while according approval for construction of residences of the Speaker and the Deputy Speaker scrupulously took into consideration about the architectural elegance of the open space and the green fields of the National Assembly Complex. The Government also critically examined whether proposed construction will disparage the architectural beauty of the National Assembly Complex. The relevant portion of the said Memo is extracted below:
96Òwb¤œ ¯^vÿiKvix Avw`ó nBqv RvbvB‡Z‡Qb †h, weMZ 6-4-98 Zvwi‡L †k‡ievsjv
97bMi¯’ wW-1 I wW-2 cøU `yBwU‡Z ¯’vcZ¨ Awa`ßi KZ…©K cÖYxZ bKmv †gvZv‡eK
98MYc~Z© Awa`߇ii D‡`¨v‡M gvbbxq ¯úxKvi I gvbbxq †WcywU ¯úxKv‡ii evm feb
99wbg©v‡Yi wewfbœ w`K m¤ú‡K© gvbbxq M„nvqY I MYc~Z© gš¿x, RvZxq msm`
100mwPevj‡qi mwP‡ei Dcw¯’wZ‡Z gvbbxq cÖavbgš¿x‡K cÖavb cÖ‡KŠkjx I cÖavb
101=18=
102¯’cwZi eªxwdsKv‡j wZwb Av‡jvP¨ `yBwU evm feb wbg©vY cÖK‡íi wewfbœ w`K, Rwg
103e¨env‡ii cwigvY, ¯’vcZ¨ bKkvi mv‡_ Ab¨vb¨ Bgvi‡Zi wWRvB‡bi mvgÄm¨Zv I
104¯’cwZ jyBm AvB Kvb KZ…©K cÖYxZ g~j bKkv‡Z D³ evm fe‡bi Rb¨ cwiKwíZ
105¯’vb, msm` feb GjvKv‡Z fwel¨r cÖKí ev¯Íevq‡bi Rb¨ mxwgZ Rwgi cÖvc¨Zv
106Ges wW-1 cø‡Ui Rwg evm fe‡bi Rb¨ e¨env‡ii †ÿ‡Î mswkøó †Lvjv RvqMvwUi
107†mŠ›`‡h©i webó BZ¨vw` cysLvbycsy Liƒ‡c ch©v‡jvPbv c~e©K weKí e¨e¯’v wnmv‡e
108gvbbxq ¯úxKvi I gvbbxq †WcywU ¯úxKv‡ii evm feb wbg©v‡Yi Rb¨ msm` moK
109bs we Gi cv‡k¦© 1.37 GKi Rwg wbw`©ó Kwiqv w`qv‡Qb|Ó
110It reveals from the Master Plan of May 2002 (Annexure-1) that the residences were planned to be constructed at D(1) and D(2) area adjacent to which construction of residences have been made on the supervision of Louis Kahn himself. The site for construction of the said residences was selected after careful scrutiny of the plan of the site next to Road B in the Master Plan of 2002. Therefore, we find that the construction of the residences of the Speaker and the Deputy Speaker will not diminish the aesthetic value and the architectural beauty of the National Assembly Complex.
111On going through the impugned judgment and order dated 21.06.2004 passed by the High Court Division it is seen that Mr. Mahmudul Islam, the learned senior Advocate being appointed amicus curiae by the court submitted in the following way-
112“……it has to be examined whether the open space being used
113for construction of the house for the Speaker and the Deputy
114Speaker was meant for public use and the right of the public
115has to be considered alongside the need of the government,
116which is also acting in the public interest. He submitted that
117=19=
118this Court ought not to interfere in a situation where the
119government is acting in the public interest. He added that
120again, it is to be seen whether the construction is creating any
121congestion in the area or materially affecting the environment
122in order to determine whether any right of the public is
123infringed.”
124But the High Court Division in its judgment could not show how the environment is affected with the construction of the residences for the Speaker and the Deputy Speaker. In this regard our view is that the said construction of residences has been undertaken with the recommendation from the Department of Architecture by critically examining the architectural beauty of the National Assembly Complex as well as the need for open space or green field. Moreover, the said residences are not meant for an individual person, but for the Speaker and the Deputy Speaker who uphold a unique position under the Constitution of our country and in the said way the impugned project is being implemented for the public interest being the same is a state necessity.
125Again, Section 3 of the Government Building Act, 1899 provides that –
126“Nothing contained in any law or enactment for the time
127being in force to regulate the erection, re-erection,
128construction, alteration or maintenance of buildings
129within the limits of any municipality shall apply to any
130building used or required for the public service or for any
131=20=
132public purpose, which is the property, or in the
133occupation, of the Government, or which is to be erected
134on land which is the property, or in the occupation, of the
135Government:
136Provided that, where the erection, re-erection,
137construction or material structural alternation of any such
138building as aforesaid (not being a building connected
139with defence, or a building the plan or construction of
140which ought, in the opinion of Government, to be treated
141as, confidential or secret) is contemplated, reasonable
142notice of the proposed work shall be given to the
143municipal authority before it is commenced.”
144On examination of Section 3 of the Government Building Act, 1899 it appears that the said construction of residences of the Speaker and the Deputy Speaker being for the public purpose in the government land is exempted from complying with provisions of other municipal laws. Therefore, the Town Improvement Act, 1953 and the Building Construction Act, 1952 have no relevance with the construction of the residences for the Speaker and the Deputy Speaker which are being constructed on Government’s own land after obtaining clearances from the Department of Architecture and on approval of the Prime Minister, the Chief Executive of the Government as per approved plan. But the High Court Division committed error of law failing to appreciate the said matter.
145=21=
146It also deserves to mention here that the writ petitioners obtained Rule and an order of stay of the operation of any further construction of the impugned project in the High Court Division in Writ Petition No.3548 of 2003 on 18.05.2003. Against the order dated 18.05.2003 and 21.07.2003 passed by the High Court Division the writ respondents-appellants preferred Civil Petition for Leave to Appeal before this Division and obtained stay operation of the said orders till disposal of the Writ Petition. During the subsistence of stay order from this Division 100% of the construction work of the residential building for the Speaker and the Deputy Speaker has been completed. But the High Court Division without taking notice of the said completion of the construction work made the Rule absolute by the impugned judgment and order dated 21.06.2004 for which the interference by this Division is warranted.
147In view of the proposition of law and discussions made above, our considered view is that the High Court Division fell in serious error of law and the impugned judgment and order of the High Court Division warrants interference by this Division.
148In the light of the observations made above, we find merit in the submissions of the learned advocate for the appellants and therefore the impugned judgment and order dated 21.06.2004 passed by the High Court Division in Writ Petition No.3548 of 2003 is liable to be set aside.
149=22=
150Accordingly, this Civil Appeal is allowed.
151The judgment and order dated 21.06.2004 passed by the High Court Division in Writ Petition No.3548 of 2003 is hereby set aside.
152C.J.
153J.
154J. The 16th day of August, 2022 Sarwar, RRO; Total words 5078
Related summaries.
From the record to your case.
Our advocates appear before both divisions of the Supreme Court. These are the practice areas that handle matters like this one.
- Supreme Court practice in BangladeshSlips, mentioning, cause lists and appearances→
- Case JourneysHow a case moves through the courts, step by step→
- Limitation and appeal deadline calculatorKnow your last day to file→
- Curative petitions in BangladeshFinality, article 104 and the case for reform→
- Constitution guideEvery article and amendment, animated→
- Bangladesh legal glossaryBangla and English legal terms, explained→