Supreme Court Judgments, Summarised

by Barrister Tahmidur Rahman | Nov 3, 2026

Summary

The plaintiff sued in Trishal, Mymensingh for a permanent injunction against officers of Power Grid Company of Bangladesh Limited, who were building a tower for a 400 KV transmission line, which the company described as a Government priority project. The trial court granted a temporary injunction stopping them from entering the land. The appellate court set it aside, finding that notices had been served under the Electricity Rules, 2020, compensation (Tk. 10,82,269/-, according to the company) had been deposited with the Deputy Commissioner, and the injunction would hinder an urgent development work and harm public interest. The plaintiff obtained a Rule but no one appeared to press it. The Court held that the appellate court committed no error of law causing failure of justice. It added that where a suit seeks a permanent injunction against an urgent and important Government public service project, its maintainability should be decided urgently, and upheld the appellate court's fifteen working day time limit. The Rule was discharged and the stay vacated.

Issues

  1. Q1

    Whether the appellate court rightly set aside a temporary injunction restraining Power Grid Company of Bangladesh officers from entering land for construction of an electricity transmission tower, where notice had been served and compensation deposited.

  2. Q2

    Whether a suit for permanent injunction against an urgent public service project should be heard on an urgent basis.

Key points

  • The Court noted the appellate court's findings that notices were duly served on the plaintiff under the Electricity Rules, 2020 and that the compensation had already been deposited with the Deputy Commissioner.
  • The Court accepted the appellate court's view that continuing the injunction would seriously hinder construction of the electricity transmission grid line and adversely affect public interest.
  • The Court held that the appellate court committed no error of law resulting in an error in its order occasioning failure of justice in setting aside the temporary injunction.
  • The Court held that where a suit seeks a permanent injunction against an urgent and highly important public service project of the Government, its maintainability should be decided on an urgent basis, and upheld the fifteen working day time limit without adjournments except in extreme exigency.
  • The Rule was discharged, the appellate order affirmed, the trial court's injunction order set aside and the stay vacated.

where a suit is filed seeking permanent injunction against an urgent and highly important public service project of the Government the question of maintainability of such suit ought to be heard and disposed of on an urgent basis.

From the judgment, Justice Md. Ali Reza
Law considered

Code of Civil Procedure, 1908, Order XXXIX rules 1 and 2

The judgment

In the court’s own words.

Civil Revision 2665/2025, as published by the Supreme Court of Bangladesh. 8 pages, with paragraph numbers for citing.