High Court Division
Md. Shafiqul Islam v Rasel Md. Mohasin and others
Civil Revision 2665/2025 · Decided 10 March 2026
The plaintiff sued in Trishal, Mymensingh for a permanent injunction against officers of Power Grid Company of Bangladesh Limited, who were building a tower for a 400 KV transmission line, which the company described as a Government priority project. The trial court granted a temporary injunction stopping them from entering the land. The appellate court set it aside, finding that notices had been served under the Electricity Rules, 2020, compensation (Tk. 10,82,269/-, according to the company) had been deposited with the Deputy Commissioner, and the injunction would hinder an urgent development work and harm public interest. The plaintiff obtained a Rule but no one appeared to press it. The Court held that the appellate court committed no error of law causing failure of justice. It added that where a suit seeks a permanent injunction against an urgent and important Government public service project, its maintainability should be decided urgently, and upheld the appellate court's fifteen working day time limit. The Rule was discharged and the stay vacated.
Rule discharged; injunction against power grid tower vacated
- Q1
Whether the appellate court rightly set aside a temporary injunction restraining Power Grid Company of Bangladesh officers from entering land for construction of an electricity transmission tower, where notice had been served and compensation deposited.
- Q2
Whether a suit for permanent injunction against an urgent public service project should be heard on an urgent basis.
- The Court noted the appellate court's findings that notices were duly served on the plaintiff under the Electricity Rules, 2020 and that the compensation had already been deposited with the Deputy Commissioner.
- The Court accepted the appellate court's view that continuing the injunction would seriously hinder construction of the electricity transmission grid line and adversely affect public interest.
- The Court held that the appellate court committed no error of law resulting in an error in its order occasioning failure of justice in setting aside the temporary injunction.
- The Court held that where a suit seeks a permanent injunction against an urgent and highly important public service project of the Government, its maintainability should be decided on an urgent basis, and upheld the fifteen working day time limit without adjournments except in extreme exigency.
- The Rule was discharged, the appellate order affirmed, the trial court's injunction order set aside and the stay vacated.
where a suit is filed seeking permanent injunction against an urgent and highly important public service project of the Government the question of maintainability of such suit ought to be heard and disposed of on an urgent basis.
In the court’s own words.
Civil Revision 2665/2025, as published by the Supreme Court of Bangladesh. 8 pages, with paragraph numbers for citing.
1Bench:
2Mr. Justice Md. Ali Reza
3Civil Revision No. 2665 of 2025
4Md. Shafiqul Islam
5……petitioner
6-Versus-
7Rasel Md. Mohasin and others
9No one appears for the petitioner
10Mr. Sayid Golam Hafiz with
11Mr. Md. Rezaul Karim, Advocates
12……for the opposite parties
13Heard on: 25.02.2026 and 05.03.2026
14Judgment on: 10.03.2026
15In the instant revision Rule was issued on 30.06.2025 calling upon the opposite parties 1-9 to show cause as to why the judgment and order dated 30.04.2025 passed by the learned Senior District Judge, Mymensingh in Miscellaneous Appeal No. 92 of 2024 allowing the appeal thereby reversing the order dated 14.10.2024 passed by the learned Senior Assistant Judge, Trishal, Mymensingh in Other Class Suit No. 288 of 2024 allowing the application for temporary injunction filed by the plaintiffs should not be set aside and/or such other of further order or orders passed as to this Court may seem fit and proper.
16The petitioner as plaintiff instituted Other Class Suit 288 of 2024 in the Court of the Senior Assistant Judge, Trishal, Mymensingh seeking a decree for permanent injunction. Along with the plaint the plaintiff also filed an application for temporary injunction under Order 39 Rules 1 and 2 of the Code of Civil Procedure.
17On the other hand the defendants 1, 2 and 3 entered appearance and filed a written objection contending inter alia that they are officers of Power Grid Company of Bangladesh Limited under the Power Division of the Ministry of Power Energy and Mineral Rosources of the Government of Bangladesh and they are engaged in establishing power transmission lines throughout the country and carrying out related works. The trial Court by order dated 14.10.2024 allowed the application for temporary injunction restraining the defendants from entering into the suit land and from dispossessing the plaintiffs therefrom.
18Being aggrieved by the said order dated 14.10.2024 defendant 2 preferred Miscellaneous Appeal 92 of 2024 before the Court of the District Judge, Mymensingh. In the said appeal the defendant also filed an application for stay of the order of temporary injunction. After hearing the parties the
appellate Court allowed the miscellaneous appeal and set aside the order of injunction by judgment and order dated 30.04.2025.
19As against the said judgment and order the plaintiff preferred the instant civil revision before this Court and obtained Rule along with an order of stay on 30.06.2025. However when the matter appeared in the cause list for hearing on 25.02.2026 and 05.03.2026 none appeared on behalf of the petitioner to press the Rule.
20Mr. Sayid Hafiz, the learned Advocate appearing on behalf of the opposite party by filing a counter affidavit submits that the Government of the People’s Republic of Bangladesh, the Government of the People’s republic of China and the Power Grid Company are jointly implementing a project titled “Power Grid Network Strengthening Project under PCCB-100” founded by PGCB and approved by ECNEC as a priority project for ensuring reliable power transmission across the country and for addressing the prevailing power crisis. The present subject matter relates to the civil work of Tower 46/1 of the Kaliakoir-Shambhuganj 400 KV Double Circuit Transmission Line under the aforesaid project. He further submits that in accordance with Rule 3(7)
21of the Electricity Rules 2020 the Deputy Commissioner issued a public notice on 20.12.2021. When the Power Grid authority initiated soil testing at the location of Tower 46/1 one of the landowners namely Most. Ozifa Khatun for the first time raised resistance and filed Other Class Suit 300 of 2022 seeking permanent injunction along with an application for temporary injunction.
22The said application for injunction was allowed on 26.02.2023. Being aggrieved thereby the Power Grid Authority preferred Miscellaneous Appeal 32 of 2023 but the appellate Court affirmed the order of the trial Court by judgment and order dated 15.11.2023. Against the said judgment the Power Grid authority filed Civil Revision No. 2041 of 2024 in which Rule was issued and an order of stay was granted on 20.05.2024.
23Thereafter the plaintiff preferred Civil Petition for Leave to Appeal No. 2391 of 2024 before the Appellate Division challenging the interim order dated 20.05.2024 which was disposed of on 24.11.2025.
24It is further submitted that the Power Grid authority included the name of the present plaintiff for awarding compensation in accordance with law and after proper
assessment deposited a sum of Tk. 10,82,269/- as compensation along with a forwarding letter dated 14.01.2024 through cheque No. CDC-2678278 dated 10.01.2024 to the office of the Deputy Commissioner. Subsequently all relevant procedural formalities were updated up to 03.11.2024.
25During the process of awarding compensation the plaintiff instituted the present Other Class Suit No. 288 of 2024 seeking permanent injunction against the government project and prayed for temporary injunction therein. The trial Court allowed the application for injunction by order dated 14.10.2024.
26Being aggrieved thereby defendant No. 1 preferred Miscellaneous Appeal No. 92 of 2024 which was allowed by the appellate Court on 30.04.2025. Against the said judgment the plaintiff preferred the instant revision and obtained Rule along with an order of stay on 30.06.2025.
27The learned Advocate for the opposite party submits that the trial Court failed to consider the relevant provisions of the Electricity Rules, 2020 wherein it has been provided that construction of electricity transmission towers shall not be obstructed in any circumstances. He further submits that the prayer for injunction is barred under section 56(d) of the
Specific Relief Act inasmuch as the petitioner can be adequately compensated in the event of implementation of the project.
28Heard the learned Advocate for the opposite party and perused the materials on record and considered the laws relevant thereto.
29From the order passed by the trial Court it appears that the trial Judge observed that although construction of electricity towers is a work of public importance and although under section 56 of the Specific Relief Act injunction cannot ordinarily be granted against works of public importance nevertheless since the defendants prima facie appeared to have violated the provisions of the Electricity Rules and there was apprehension of irreparable loss to the plaintiff an order of temporary injunction was warranted.
30On the other hand the appellate Court by its order dated 30.04.2025 held that the trial Court granted the order of injunction against an urgent development work relating to construction of electricity towers and transmission lines under the Power Grid project. The appellate Court further found that notices had been duly served upon the plaintiff in accordance with the Electricity Rules, 2020 and the compensation amount
had already been deposited with the office of the Deputy Commissioner by the defendants.
31The appellate Court also observed that continuation of the order of injunction would seriously hinder the construction of the electricity transmission grid line and thereby adversely affect public interest. In such circumstances the order of temporary injunction was liable to be set aside.
32In view of the above I find that the appellate Court committed no error of law resulting in an error in such order occasioning failure of justice in setting aside the order of temporary injunction passed by the trial Court.
33It is also to be observed that where a suit is filed seeking permanent injunction against an urgent and highly important public service project of the Government the question of maintainability of such suit ought to be heard and disposed of on an urgent basis. In this regard the direction of the appellate Court fixing a time limit of fifteen working days for disposal of the matter appears to be lawful and justified in the interest of public welfare and proper administration of justice and such direction has got to be maintained by the trial Court without affording any adjournment to any of the parties except extreme exigency.
34In the result I find no merit in this Rule.
35Accordingly, the Rule is discharged.
36The judgment and order of the appellate Court is hereby affirmed and the order passed by the trial Court is set aside.
37The order of stay passed by this Court stands vacated.
38The office is directed to communicate a copy of this judgment and order to the concerned Court at once.
39Md. Ali Reza, J: Naher-B.O
Related summaries.
From the record to your case.
Our advocates appear before both divisions of the Supreme Court. These are the practice areas that handle matters like this one.
- Supreme Court practice in BangladeshSlips, mentioning, cause lists and appearances→
- Case JourneysHow a case moves through the courts, step by step→
- Limitation and appeal deadline calculatorKnow your last day to file→
- Curative petitions in BangladeshFinality, article 104 and the case for reform→
- Constitution guideEvery article and amendment, animated→
- Bangladesh legal glossaryBangla and English legal terms, explained→











