Summary

RAJUK (Rajdhani Unnayan Kartipaksha, the capital development authority) invited a re-auction tender in 2004 for a plot at Bangla Motor, Dhaka. The petitioner became the highest bidder at Tk.43,11,000/- and deposited Tk.5 lac as earnest money, and RAJUK's Board decided to hand over the plot. A rival's writ petition paused the process; it was later discharged for non-prosecution. RAJUK then sent the matter to the Ministry for an opinion on whether to hand over the plot or hold a fresh auction because prices had risen, and ignored the petitioner's requests. The High Court Division found that the same Board Meeting had accepted and confirmed the petitioner's bid, that RAJUK could dispose of the land under section 101 of the Act of 1953 without the Ministry's opinion, and that its silence was a denial of justice. The writ petition was maintainable. The Rule (order to show cause) was made absolute and RAJUK was directed to complete the allotment within 6 months on receipt of the balance price.

Issues

  1. Q1

    Whether RAJUK could refer the matter to the Ministry of Housing and Public Works for an opinion on a fresh auction after it had accepted the petitioner's highest bid for the plot.

  2. Q2

    Whether a writ petition challenging RAJUK's Board Meeting decision and its failure to hand over the plot to the highest bidder was maintainable.

Key points

  • The Board Meeting decision showed that the petitioner's bid, being the highest, was accepted and confirmed by RAJUK.
  • Although the Ministry of Housing and Public Works is RAJUK's controlling authority, there was no necessity to send the matter to the Ministry for an opinion, since RAJUK had authority under section 101 of the Act of 1953 to dispose of the land.
  • RAJUK's silence after receiving the notice demanding justice was a denial of justice, and its dilatory tactics at the behest of interested quarters were unfair.
  • A writ petition challenging the unreasonable and arbitrary decision of RAJUK's Board Meeting was maintainable.
  • The Rule was made absolute without costs, and RAJUK was directed to proceed with allotment of the plot to the petitioner on receipt of the balance amount and complete the process within 6 months.

After receiving the notice of demanding justice, the respondent RAJUK has kept silent which is nothing but denial of justice. Respondent 1 has started dilatory tactics for collateral purpose at behest of interest quatters which is found unfair.

From the judgment, Justice Bhishmadev Chakrabortty
Law considered

Town Improvement Act, 1953, section 101

The judgment

In the court’s own words.